← Back to Knowledge

In meetings with investors, domestic and overseas alike, one phrase comes up almost every time: "long-term PPA." The intent — to own a storage asset on a stream of long-term fixed income — is exactly right. Just one word is off. Because a battery does not generate net electricity, the kind of PPA that sells a fixed volume of energy (kWh) at a fixed price, the way solar or wind does, does not map onto a storage asset.

And the return without any fixing has already been put on paper, in a public estimate. In the sensitivity analysis the Mitsubishi Research Institute (MRI) submitted to a Ministry of Economy, Trade and Industry (METI) working group, even with capacity-market income added, the base case at a CAPEX of ¥60,000/kWh returns an IRR of −1.5%. Merchant operation alone does not turn a profit, even on the public assumptions. That is precisely why the question "which contract fixes the revenue" decides whether the project works.

Without fixing, even the public estimate can be in the red. On MRI's numbers, even with capacity-market income the base-case IRR is −1.5% (CAPEX ¥60,000/kWh). The path to the black is either to cut CAPEX below ¥50,000/kWh, or for wholesale spreads to swing to the upside (on an upside assumption with CAPEX ¥30,000/kWh, IRR is about 14%). Fixed income is the device that lifts that loss-making floor.
How to read this piece: Regulatory state as of June 2026. Primary readers are domestic and overseas institutional investors. Figures start from published primary information (corporate timely disclosures, OCCTO, METI, the Ministry of Finance and others) and public estimates; equity IRRs use ScienceX's stated-assumption model (a generic 47 MW / 188 MWh extra-high-voltage example). Where a value is undisclosed — such as the unit price of a bilateral domestic contract — we write "undisclosed" and make no guesses. Overseas figures (US, UK, Germany) are proxies on different assumptions and cannot be applied directly to Japan. This is not investment, tax or legal advice.
Scope of this piece
SUBJECT
Fixed-income contracts5 types compared
IF UNFIXED
−1.5% (public estimate, incl. capacity market)
TOLLING
18.6% (model, 75% debt)
LDA
≈5% (anchored by design)
DOMESTIC OFFTAKE
20years (every confirmed deal)
PRIMARY READERS
Domestic & overseas investors, buyers, financiers

01 — A "PPA" and a storage contract are different things

First, let us align the vocabulary. A generation PPA is a contract to buy and sell energy (kWh) at a fixed price. A virtual PPA goes further: no electrons move at all, only the environmental value (non-fossil certificates) is traded. The virtual PPA signed in June 2026 between ENEOS Renewable Energy and NSK in Kyushu is the textbook case — environmental value alone, supplied for about 15 years from a roughly 54 MW solar plant fitted with about 130 MWh of batteries. Here the battery's job is to firm the solar output; it is not a contract that fixes the revenue of a storage asset itself.

What a long-term storage contract fixes is not energy, but capacity and dispatch rights. Who carries the market-price risk — that is the single axis on which the true nature of these contracts can be read.

NameWhat it fixesWhere market-price risk sitsFit for storage
Generation PPA (physical)Sells kWh at a fixed priceBuyer takes it; generator carries volume riskNot a fit (storage does not sell through)
Virtual PPAEnvironmental value (certificates) onlyMutual hedge via contract-for-differenceUsed with co-located solar (ENEOS × NSK)
Offtake / tollingProvides capacity and dispatch rights for a fixed feeOfftaker carries all of itThe core of storage
Floor + revenue shareGuarantees a minimum return, shares the upsideDownside = offtaker / upside = sharedA fit
Full-service optimisation (managed)Operations mandate, success feeAsset owner carries itA fit (merchant in character)
LDA (Long-term Decarbonisation Auction)20 years of capacity revenueThe scheme (counterparty is OCCTO)A fit

In Japan, "offtake contract" and "tolling contract" are used almost interchangeably in practice (they are not perfectly synonymous as a matter of regulatory definition). The scheme Tokyo Gas calls an "offtake contract" is the same shape as a thermal-plant toll: the SPC that owns the battery hands over dispatch rights, receives a fixed fee, and the market-price risk is taken off its hands. We treat the two as synonymous here.

02 — Five options on one map

With the vocabulary aligned, plotting the options on two axes — the firmness of the revenue (predictability) and the room for equity upside — brings out the differences in character. "PPA," a word from the generation world, does not sit on this map at all.

Predictability (revenue firmness) → Low High Equity upside → High Low PPA = a generation term (does not map to storage) Merchant Base IRR −1.5%, high variance Floor + RS (10y) Downside floor + upside share Tolling (20y) Equity 18.6% (leverage) LDA (20y) Capped at ≈5% by design
Figure — A map of the four options by revenue firmness (predictability) and room for equity upside

The map shows that predictability and upside are not necessarily inversely related. Because tolling delivers certain revenue, it can carry thick debt, so even a project IRR in the 6% range produces an equity IRR in the 18% range (top right). The LDA, by contrast, has the strongest predictability of all, yet by design it gives up the upside (bottom right, more below). Merchant has the widest room to swing higher, but it swings far enough that even a public estimate can be in the red (top left).

Before going further, it is worth orienting the map against the markets a Western investor already knows. Japan runs the same toolkit — minus the standalone-storage PPA, and minus a federal investment tax credit. The table below maps each Japanese contract onto its closest equivalent in the United States, the United Kingdom and the EU.

Contract (Japan)United StatesUnited KingdomEU (Germany)
Merchantbalancing + capacity + JEPXERCOT merchant (no capacity market)Wholesale + Balancing Mechanism + Capacity MarketEPEX intraday / FCR merchant
Capacity marketCAISO Resource Adequacy (RA); PJM capacityCapacity Market (T-1 / T-4)Limited capacity remuneration
Tolling / offtakeTokyo GasStorage PPA structured as a toll; RA contract (CAISO, ERCOT)Tolling (Gresham House × Octopus; Eku × SmartestEnergy)Tolling (RWE, Vattenfall, terralayr)
Floor + revenue shareBisonRevenue floor / synthetic toll (GridBeyond)Floor (Gresham House, ≈£52k/MW·yr)Emerging
LDAgovernment-backed, 20yNo federal analogue; §48E ITC insteadLDES cap-and-floor (Ofgem, 8h+, awards summer 2026)No direct analogue
[ PPA ]Solar / wind PPA (not standalone storage)CfD / PPA (generation)PPA (generation)

Mapping by ScienceX for orientation. The equivalents are approximate; market rules, tenor and counterparties differ. Overseas figures are proxies and cannot be applied directly to Japan.

Read against that mirror, the same five Japanese options line up cleanly on contract, tenor, price, return and domestic track record:

OptionContract / tenorPrice (sell side)ReturnMarket-price riskJapanese track record
Merchantbalancing + capacity + JEPXNo contractPublic estimate base −1.5% (incl. capacity market, CAPEX ¥60k). 0.4% at CAPEX ¥50k; 14% at CAPEX ¥30k with wholesale upsideOwnerTanagawa 99 MW (Japan's first full-merchant PF)
Tolling= Japan's "offtake"20 yearsDomestic undisclosed / overseas pure toll ≈ £57k/MW·yr (≈ ¥11.4m/MW·yr)Project 4–6.6%, yet equity 18.6% via leverage (toll + capacity market, 75% debt). Pure toll alone is single-digitOfftakerTokyo Gas × Eku Hirohara 30 MW, × Renova Ishikari 30 MW, × Equis Ashiya 50 MW (each 20y)
Floor + RS10 yearsOverseas floor ≈ £44–52k/MW·yr (≈ ¥8.8–10.4m/MW·yr)Minimum guaranteed + upside sharedDownside = offtaker / upside = sharedBison × Englehart (10y, agreed in principle)
LDA20 yearsWeighted average 5.8 → 6.8 → 11.1 (¥10k/kW·yr) across rounds (all decarbonised sources; storage-specific clearings undisclosed)By design anchored ≈5% (return cap + ~90% clawback of other-market income)Scheme (upside surrendered)Various bidders. Storage-specific clearings permanently undisclosed
[ PPA ]No intrinsic value for storageENEOS × NSK = environmental value only, ~15y (a different thing from fixing revenue)

¥ conversions are illustrative at £1 ≈ ¥200, $1 ≈ ¥155, €1 ≈ ¥165, not actual contract values. Domestic toll / offtake / floor unit prices are undisclosed between the parties. The 47 MW equity IRR is a stated-assumption generic model.

03 — What the contracts are: four types and the clauses that matter

A long-term storage contract sorts into four types by who carries the market-price risk. In every case the asset is, as a rule, owned by the owner side (the SPC), and the dispatch rights pass to the offtaker.

TypeWho carries market-price riskJapanese name / examples
Pure tollingcapacity reservation / lease typeOfftaker carries all of itTokyo Gas "offtake contract"; MIRARTH × PowerX
Floor + revenue shareDownside = offtaker / upside = sharedBison × Englehart CTP (10y, a Japanese first)
Full-service optimisationmanaged operationsOwner retains itTokyo Gas optimisation (Renova 165 MW); PowerX aggregation
HybridPart toll + part merchantOverseas (terralayr "LAYR" and others)

What the contract nails down is the same set of clauses an investor would recognise from London, Houston or Frankfurt: availability guarantees (fee reductions on a shortfall), capacity guarantees (including degradation), whether the fee is CPI-linked, responsibility for charging energy, dispatch rights and cycle limits, and credit support (parent guarantee, letter of credit, rating triggers). Because the standard contracts are confidential in Japan, the concrete levels have to be inferred from markets where disclosure runs further — and there, the United States, the United Kingdom and Germany each tell a slightly different version of the same story.

The United States: storage PPAs are usually tolls, plus RA and synthetic floors

In the US, a storage PPA is most often structured as a tolling arrangement: the utility supplies the charging energy, because developers do not want to take input-price risk and the utility is better placed to bear it. In California, load-serving entities carry capacity procurement obligations under the Resource Adequacy (RA) program, and RA contract prices have risen year after year; with an RA contract in place, the average battery could still have earned on the order of $178/kW·yr in total wholesale revenue across 2025. In ERCOT, which has no capacity market, revenue is far more volatile, and tolling is spreading as a de-risking tool — five operating projects under known tolls, with seven more expected online by the end of 2026. Where owners want certainty without a full toll, optimisers such as GridBeyond now offer revenue-floor and synthetic (virtual) toll contracts in ERCOT and CAISO, underwritten by investment-grade partners — the same downside-protection logic as the UK floors and Japan's Bison deal.

Germany: pure tolls, disclosed in euros

German tolls run roughly €110,000–150,000/MW·yr on tenors of 5–7 years (10 at most), with signed examples including Stendal (104.5 MW, 7 years, contract value €85–95m), Vattenfall, and RWE (50 MW, 5 years). These are the clearest disclosed unit prices in the European market.

At the contract's threshold, read through to how the counterparty books it. Overseas, there are cases where the toll fee is expensed (OpEx) and treated off-balance-sheet (RWE × terralayr explicitly call theirs "balance-sheet-light"). In Japan, the new lease accounting standard becomes mandatory from April 2027, and if tolling is identified as a lease it can sit on-balance-sheet for the offtaker (the lessee). The same contract can land on the counterparty's balance sheet in opposite ways in Japan and abroad — and that affects appetite to sign.

04 — How many years: domestic offtake is 20 years as standard

On tenor, every domestic offtake we could confirm was 20 years. Hirohara, Ishikari, Ashiya, and the HDRE (HD Renewable Energy) deal added in April 2026 — all about 20 years, in line with the 20-year tenors of the capacity market and the LDA. Shorter domestic offtakes of 10–15 years cannot, at present, be confirmed in public disclosure. Only the floor contract is short, at 10 years, and that is a different form from offtake. Overseas tolling ranges from 5 to 15 years, and the rule of thumb for bankability is roughly 10 years or more with an investment-grade offtaker. Because tenor sets the loan tenor, the floor's 10 years is a constraint in PF design.

05 — How much you make: the floor without fixing, the overseas levels, the LDA ceiling

This is the core. In order: the case without fixing, the overseas fixed levels, the LDA's effective return, and then the same 47 MW model.

−1.5%MRI base IRR (incl. capacity market, CAPEX ¥60k/kWh)
18.6%47 MW model, tolling equity IRR (75% debt, DSCR 1.31x)
≈5%LDA effective return (anchored by design)

The floor without fixing. On the public estimate, the base-case IRR is −1.5%. Turning a profit means either cutting CAPEX below ¥50,000/kWh or wholesale spreads swinging to the upside (on an upside assumption with CAPEX ¥30,000/kWh, IRR is about 14%). Merchant carries the dream of the upside, but on the public assumptions its floor is in the red.

The fixed level is undisclosed in Japan. Tokyo Gas, PowerX, Bison and MIRARTH alike record only "20 years (or 10), fixed amount"; not one publishes a figure that can be normalised to ¥/kW. That is not a gap in the record — it is a finding about the state of the market. The reference level is built from markets where disclosure runs further. In the UK, a roughly 2-year toll is on the order of £57k/MW·yr (≈ ¥11.4m/MW·yr); a 10-year-class floor is £44–52k/MW·yr (≈ ¥8.8–10.4m/MW·yr). Named UK deals add texture: Gresham House × Octopus (≈£57k/MW·yr, including about £10k of capacity market), the Gresham House floor (≈£52k/MW·yr, 7 years and over, performance-conditioned), Eku × SmartestEnergy at Ocker Hill (99 MW / 198 MWh, 10 years — the UK's first debt-backed toll), and Drax's West Burton C (250 MW / 500 MWh, 10 years, CPI-linked).

Overseas, there are even moments where safety (the floor) pays more than risk. UK merchant revenue fell from £84–86k/MW·yr in December 2024 to about £41k/MW·yr by February 2026 — nearly halved year on year. The floor (£44–52k) is closing on, and in places overtaking, merchant outcomes. A fixed contract is meant to be a trade where you give up the upside to buy safety; right now the inversion is real — the fixed level is the higher one. In the US the same volatility is on display: ERCOT revenues swing sharply year to year, while California RA prices have risen, so a contracted asset can out-earn a merchant one. That is why demand for floor and toll contracts is growing structurally across the Western markets.

The LDA is the one contract whose sell-side price is publicly fixed. Weighted-average clearing prices rose across rounds: 5.8, 6.8 and 11.1 (¥10k/kW·yr) for the first, second and third (figures for decarbonised sources as a whole; storage-specific clearings are permanently undisclosed). But the LDA caps the return that can be built into a bid at a pre-tax WACC of 5% (±1%), and then claws back about 90% of any income earned in other markets after the fact. Between these two constraints, the winner's effective return is anchored by the scheme at roughly 5%. Predictability is the strongest of all; the upside is shut off, by design, from the start. From the third round, continuous discharge of six hours or more became a requirement, and the lithium-ion allocation was tightened from 1 GW to 0.4 GW.

The LDA has a UK cousin: the cap-and-floor. Ofgem's cap-and-floor scheme for long-duration electricity storage (LDES), modelled on the UK interconnector regime, gives a government-backed revenue floor (income topped up if revenues fall below the floor) and returns most or all revenue above a "soft" cap to consumers. The first window drew 171 bids (52.6 GW); 77 projects (28.7 GW) cleared eligibility, lithium-ion dominating; the duration bar is eight hours or more, and final awards are due in summer 2026. Like the LDA, it trades the upside for a regulated floor — predictability bought by surrendering the top end. The mechanics differ (the LDA fixes a capacity price by auction and claws back other-market income; the cap-and-floor sets a floor and a soft cap around a fair return), but both anchor the return near a regulated rate. A UK investor reading the LDA is, in effect, already fluent in it.
On the same 47 MW asset, the contract changes the shape of the return. Tolling sits in the lower band on project IRR at 6.6%, yet because the revenue is certain it can carry debt to about 75%, so the equity needed falls to a minimum. The result is an equity IRR of 18.6% (minimum DSCR 1.31x). That 18.6%, though, is on a "toll + capacity market" hybrid assumption, with capacity-market income (held by the owner) added to the toll fee. The source of the gain is not high project profitability; it is the high leverage that certainty makes possible. For an investor, this is exactly where the Japanese market opens.

Domestic toll fees are undisclosed between the parties. The 47 MW equity IRR is a stated-assumption generic model, not an actual deal value. This 18.6% is on a hybrid assumption where capacity-market income (about 40% of revenue) is held by the owner; on a pure toll that hands the capacity market to the offtaker as well, the same toll fee drops equity IRR to single digits. To reach 18% on a pure toll alone, the toll has to rise to about 2.6× the overseas benchmark (£57k/MW·yr ≈ ¥950/kW·month), or CAPEX has to fall by about half (toward Chinese-cell levels) — see §§06–07.

06 — Running the same 47 MW under four contracts

From here, the contents of that 18.6%. Taking an extra-high-voltage 47 MW / 188 MWh (4-hour) asset as a generic example, we run the same hardware under four contracts — ① balancing-led, ② capacity + wholesale, ③ LDA (6-hour), ④ tolling + capacity market — and line up project IRR, equity IRR, DSCR and payback period, with the assumptions stated.

Subject (generic example)
GRID CAPACITY
47MW (EHV, send-out)
STORAGE
188MWh (4 hours)
CAPEX
≈¥10bn(≈ ¥53k/kWh, ≈ $65m)

The remaining assumptions are as follows. Effective tax rate about 31.5% (after size-based enterprise tax and the special defence corporate tax); useful life 17 years; annual degradation about 1% (allowing roughly 4 hours at commissioning to fall to 3 hours at contract end); round-trip efficiency 85%, DoD 90%. On financing, ④ tolling and ③ LDA, with high certainty suited to long-term debt, take about 75% debt at 3.0% over 18 years, while ① and ② merchant, with variable revenue that does not support much debt, take about 40% at 3.5% over 10 years. Market assumptions (base): balancing ΔkW at ¥4/ΔkW·30min (50% clearing), capacity market about ¥11k/kW·yr, JEPX day spread ¥20/kWh, one cycle a day, LDA fixed at ¥30k/kW·yr (about 90% of other-market income clawed back). Only ③ LDA is sized at 6 hours / 282 MWh / CAPEX about ¥15bn. And ④ tolling is a "toll + capacity market" hybrid in which the owner holds the capacity-market income — about 40% of ④'s total revenue. The return on a pure toll that hands the capacity market to the offtaker as well is shown in §07.

The table below is the central result, setting out investment metrics for the same 47 MW hardware run under four contracts.

Metric (same 47 MW asset)① Balancing-led② Capacity + wholesale③ LDA (6h)④ Tolling + capacity market
CAPEX¥10.0bn¥10.0bn¥15.0bn¥10.0bn
Equity¥6.0bn¥6.0bn¥3.75bn¥2.5bn
Project IRR13.3%9.8%3.5%6.6%
Equity IRR17.6%12.7%6.5%18.6%
Minimum DSCR2.83x2.22x1.04x1.31x
Payback (approx.)7 yrs9 yrs14 yrs11 yrs
20-year NPV+¥7.43bn+¥3.92bn−¥1.68bn+¥1.28bn
PredictabilityLowLow–mediumHighHigh

④ tolling is on a "toll fee + capacity-market income (held by the owner)" hybrid assumption. On a pure toll that hands the capacity market to the offtaker as well, the same toll fee drops equity IRR to single digits (see §07).

Take equity IRR alone and ④ tolling (18.6%) and ① balancing (17.6%) run close. But their insides are opposite. The figure below sets each contract's project IRR (the business's earning power) against its equity IRR (the shareholder's return).

Figure / Project IRR vs Equity IRR (4 contracts) Project IRR Equity IRR 0% 10% 20% 13.3 17.6 ① Balancing 9.8 12.7 ② Capacity + wholesale 3.5 6.5 ③ LDA 6.6 18.6 ④ Tolling ④ has the lowest project IRR (6.6%) yet the highest equity IRR (18.6%)
Figure — Project IRR and equity IRR by contract for the same 47 MW asset (stated-assumption model)

The contract with the lowest project IRR has the highest equity IRR

④ tolling sits in the lower band on project IRR at 6.6%, yet its equity IRR is the highest at 18.6%. Not because the business is more profitable. Because the revenue is certain, it can carry debt to about 75%, so the equity needed is the smallest, at ¥2.5bn. Equity IRR moves roughly as "(project IRR × total investment − interest × debt) ÷ equity." Even at a project IRR of 6–7%, with 75% debt at 3%, leverage lifts the thin equity. The source of the gain is not "high project profitability" but "the high leverage that certainty makes possible."

The flip side: this inversion does not hold unconditionally. If the certainty breaks, the thick debt cannot be raised and the equity IRR sinks. There are three conditions for it to hold.

CONDITION 01

Post-stress DSCR ≥ 1.2–1.4x

Fixed fee or LDA fixed income must cover debt service by this multiple even in a conservative case. ③ LDA sinks to 1.04x at realistic clearing prices, and this is where it breaks.

CONDITION 02

Investment-grade offtaker

The payer of the fixed fee (a major utility, gas company, etc.) must be investment-grade equivalent, or backed by a parent guarantee. Weak credit means no long-term debt.

CONDITION 03

Tenor alignment

Contract tenor (20 years) ≥ loan tenor ≥ asset life. Price in the merchant tail at the end, and the DSCR through it.

CONTRAST: MERCHANT

High IRR, but you can only borrow thin

① balancing looks high at an equity IRR of 17.6%, but because revenue is variable, debt is capped at about 40% (equity ¥6.0bn), and a regulatory change can pull the assumptions apart.

Reading the four contracts

④ tolling (toll + capacity market) is the lead. A toll fee of ¥1,500/kW·month (¥18k/kW·yr) plus capacity-market income (held by the owner) gives an equity IRR of 18.6% and a minimum DSCR of 1.31x. No market operation is needed, and because the offtaker carries the price risk it is the most stable. The premise is the offtaker's credit. But on a pure toll that hands the capacity market to the offtaker as well, the same ¥1,500/kW raises only a little over 40% in debt, and equity IRR falls to single digits (see §07).

② capacity + wholesale is the upside. You can reach for more through wholesale arbitrage and the capacity market. It is favoured in areas with high JEPX spreads or capacity prices, but because revenue is variable, debt stays around 40%.

① balancing-led is high-return, high-volatility. Project IRR is the highest at 13.3% and payback the fastest at 7 years, but the March 2026 balancing-market reform (price cap ¥15, volume tightened to 1σ) can pull the assumptions apart. The headline IRR and its repeatability are different things.

③ LDA is condition-dependent and the weakest. Six hours / 282 MWh is mandatory, so CAPEX is about 1.5× (¥15bn). It works if you set the fixed income at ¥30k/kW·yr, but at realistic clearing levels (a view in the mid-¥20k thousands) the DSCR falls below 1 and it cannot be structured. The viability depends on a bet on the clearing price. It works only if the equipment cost can be halved, or the clearing comes in high.

07 — The toll fee decides most of the equity (a pure toll is single-digit)

④ tolling's return moves almost in proportion to the toll fee. A difference of a few hundred yen a month swings the equity IRR a long way. First, the case of a hybrid in which the owner holds the capacity-market income.

Toll feeAnnualisedEquity IRRMinimum DSCRAssessment
¥1,200/kW·month¥14.4k/kW·yrFalls (marginal)≈1.0DSCR nears 1, debt tightens
¥1,500/kW·month¥18.0k/kW·yr≈18.6%1.31xFinanceable, the base level
¥1,800/kW·month¥21.6k/kW·yr≈25%ThickUpside, room to negotiate

The table above is on a hybrid assumption with capacity-market income held by the owner. Capacity-market income is about 40% of total revenue. The per-kW unit price is undisclosed between the parties.

So what about a "pure toll" that hands the capacity-market income to the offtaker as well? Because revenue is then the toll fee alone, the same ¥1,500/kW raises only a little over 40% in debt (the DSCR bites, so it cannot be stretched to 75%), and equity IRR sinks to roughly 0%. At the overseas pure-toll benchmark (£57k/MW·yr ≈ ¥950/kW·month) it is negative.

Pure toll fee (no capacity market)AnnualisedDebt raisedEquity IRR
¥950/kW·month≈ overseas £57k benchmark¥11.4k/kW·yr≈22%−8.7%
¥1,500/kW·monthsame as this model¥18.0k/kW·yr≈44%≈0%
¥2,500/kW·month≈ 2.6× overseas¥30.0k/kW·yr75%≈18.6%

To reach an equity IRR of 18.6% on a pure toll (no capacity market), the toll has to rise to about ¥2,500/kW·month (≈ ¥30k/kW·yr ≈ 2.6× the overseas benchmark), or — holding the toll at ¥1,500/kW — CAPEX has to fall to about ¥5.2bn (≈ ¥28k/kWh, Chinese-cell level, about half of current). At Japanese CAPEX (¥10bn, ≈ ¥53k/kWh), a realistic pure toll does not produce a double-digit IRR. Overseas investors can aim for a high shareholder return in Japan when their procurement can cut CAPEX. The disclosed pure-toll benchmark is roughly ¥10–15k/kW·yr (overseas); the per-kW unit price is undisclosed between the parties.

08 — Who is contracting, and over how many years

To fix, you need a counterparty that can fix. For grid-scale storage, the one party publishing 20-year, dispatch-rights-transfer, fixed-fee offtake at scale and across multiple deals, as the offtaker (the party taking dispatch rights), is at present clearly Tokyo Gas. On top of Hirohara 30 MW, Ishikari 30 MW and Ashiya 50 MW, April 2026 added about 190 MW with HDRE (HD Renewable Energy).

Offtaker / providerProject (location)SizeFormTenor
Tokyo Gas × Eku EnergyHirohara (Miyazaki)30 MW / 120 MWhOfftake20 yrs
Tokyo Gas × Renova SPCIshikari (Hokkaido)30 MWOfftake20 yrs
Tokyo Gas × Equis SPCAshiya (Fukuoka)50 MW / 201 MWhOfftake20 yrs
Tokyo Gas × HDREMiyazaki Hyuga + 4 others≈190 MW totalOfftake (HDRE's wording)≈20 yrs
MIRARTH × PowerXKanagawa Aikawa2.0 MW / 7.4 MWhTollingUndisclosed
Bison × Englehart CTPUndisclosed (agreed in principle)Floor (minimum revenue guarantee)10 yrs

Sources: Tokyo Gas (2024-04-24 / 2025-06-30), HDRE (2026-04-16), MIRARTH (2025-09-08), Kyodo PR Wire (Bison, 2025-07-07). Undisclosed items are marked "undisclosed."

⚠️ DISCLOSURE MISMATCH
The HDRE deal's "≈190 MW offtake" is described as an "offtake contract" only in HDRE's release. Tokyo Gas's own release records only an "optimisation service contract" for Aomori 149 MW (Hachinohe, Towada) and does not mention the 190 MW offtake. Because the scope of disclosure differs between the two companies, how it folds into Tokyo Gas's official tally (previously 110 MW) cannot be confirmed. We treat the discrepancy as a finding in its own right.

Look to other forms and the monopoly is starting to crack. MIRARTH and PowerX are tolling; Bison and Englehart CTP are Japan's first 10-year floor. The picture of "the only seller of fixed revenue = Tokyo Gas" is no longer accurate. The base of providers is also thickening, in the form of equity and operations.

PartyForm of involvementMain projectsTarget
Tokyo GasOfftaker + managed operationsHirohara / Ishikari / Ashiya + HDRE collaboration; Renova 165 MW operationsEHV to ~2 GW by early 2030s
Kansai Electric PowerEquity + PFTanagawa 99 MW, Kinokawa 48 MW (operating)≈1 GW in the early 2030s
Osaka GasEquity + operationsSenri 11 MW (operating), Kaminokuni and othersExpanding the storage business
Saibu Gas × Bank of FukuokaJoint study (agreed in principle)Kyushu, target operation around March 2028Investment of ¥1–3bn

Sources: each company's timely disclosure / IR and reporting (2024–2026). Saibu Gas × Bank of Fukuoka is at the agreed-in-principle stage; the SPC and contract are unannounced.

The financing precedents are now all in place. All arranged by MUFG Bank: (1) Hirohara, a fixed-revenue type built on offtake as the credit base (Japan's first storage PF); (2) Ishikari, an offtake type (about ¥5bn); and (3) Tanagawa, a full-merchant non-recourse deal repaid from market revenue alone (a Japanese first). The convention is to credit-enhance with fixed income; full merchant presumes operating expertise on the order of Kansai Electric Power.

09 — CAPEX, and the rules that tailwind fixing

≈¥68k/kWhDomestic EHV turnkey (MRI estimate)
$117/kWhBNEF turnkey global average (China $73)
30% capLDA round 3, per-country cell-manufacture cap

What squeezes the return most is CAPEX. A domestic grid-scale turnkey is estimated at about ¥68,000/kWh (about $440). BloombergNEF's global turnkey average (including system installation) is $117/kWh, and Chinese-made is $73/kWh (about ¥11,000/kWh) — a gap of more than 3× between Japan and abroad. The LDA's third round made six hours or more of continuous discharge a requirement, tightened the lithium-ion allocation from 1 GW to 0.4 GW, and imposed a "30% per-country cell-manufacture cap." The scheme brought the trade-off between reliance on cheap Chinese product and security into the design.

The subsidy Japan does not have — and the supply-chain squeeze it shares. In the US, standalone storage earns the federal §48E investment tax credit: a 30% base, above 40% (toward roughly 50%) with domestic-content and energy-community adders, and transferable for cash. The One Big Beautiful Bill Act (July 2025) spared storage from the accelerated sunset applied to wind and solar — the full credit runs through about 2032, phasing down from 2034 — but it added "foreign entity of concern" (FEOC) limits: projects beginning construction from 2026 must keep non-FEOC content above 55%, rising to 75% by 2030, or lose the credit. Japan has no equivalent federal ITC for storage; its FY2026 immediate-depreciation / 7%-credit measure may exclude tolling under a "lease use" carve-out, and the point is unsettled (see §10). But the China-supply-chain squeeze runs both ways across the Pacific: the US FEOC content floor, Japan's LDA per-country cell cap (30%) and the JC-STAR communications-layer requirement all push the same direction. Cheap Chinese cells lift the return; both regimes now price in a security discount.

The rules tailwind fixed contracts in one more way. The balancing market's price cap was cut from ¥19.51 to ¥15/ΔkW·30min (in force), and if competition does not improve, a staged reduction to ¥10 and ¥7.21 is under study. The procurement volume was tightened too. The more the upside of merchant operation is trimmed, the more the relative value of fixed income (tolling, floor, LDA) rises.

EHV and HV are different economic spheres. The long-term contracts so far (tolling, offtake, LDA) and the large market revenue are an extra-high-voltage story (roughly 10 MW and up). HV assets at the 2 MW / 8 MWh class can also join the capacity market (a battery qualifies as a firm resource at an expected capacity of 1,000 kW or more, discharging once a day for three continuous hours or more; 2 MW / 8 MWh is 4 hours, so it clears the duration test). But the balancing market requires a dedicated online line (costing tens of millions of yen to lay) from secondary reserve onward, and what can enter offline (via the simple command system) is limited to primary reserve from batteries of 1 to under 10 MW. HV is not the main subject of long-term tolling / offtake / LDA; HV revenue centres on aggregator-routed optimisation (e.g. Tokyo Gas × LifeOne, five HV sites at 2 MW / 8 MWh each).

How the cost reads also changes. The $117/kWh global average and the MRI estimate of about ¥68,000/kWh in this section are EHV / large-turnkey levels. A 2 MWh-class HV asset, where economies of scale do not bite, divides fixed costs — substation, interconnection, PCS, design, warranty — across a small capacity, so the ¥/kWh unit cost is structurally higher. Set against the global large-asset level it looks expensive, but the right comparison is a domestic deal at the same scale and the same installation conditions; the basis for judgement is not the ¥/kWh unit cost, but the net cost after subsidy (the grid-scale reference being about ¥39,500/kWh) and the revenue and IRR that asset produces.

10 — Three gates specific to the foreign investor

The gates that stand only in front of overseas capital, in brief. Each can be built into the plan if grasped in advance.

Foreign Exchange Act (FEFTA) — it comes before interconnection. The electricity business is a "core" sector under FEFTA, and generation operators of 50,000 kW or more fall within scope. A storage asset qualifies as the designated "generation business" regardless of output, and an EHV 47 MW is a core sector. Acquiring shares of an unlisted SPC requires a prior notification subject to screening even for a single share (China and others are outside the prior-notification exemption from the May 2025 amendment); the prohibition period is 30 days, up to 5 months. Completing the screening before grid interconnection becomes the critical path. This is Japan's version of CFIUS — and the amended FEFTA, submitted to the Diet and decided by Cabinet in March 2026 and enacted in May 2026, adds indirect-acquisition controls and creates a cross-ministerial Committee on Foreign Investment in Japan (a Japanese CFIUS). It comes into force on a date set by Cabinet order within one year of promulgation: enacted, with entry into force still to come.
🚩 TAX — THERE IS NO SETTLED VIEW FROM THE AUTHORITIES YET
The investment-promotion tax measure created for FY2026 (the special tax system for investment in specified productivity-enhancing equipment) allows immediate depreciation or a 7% tax credit on the acquisition value, but the text defines the scope as "for use in the business (excluding use for leasing)." Because tolling hands dispatch rights to the offtaker, if it is characterised as "use for leasing" it risks falling outside immediate depreciation. And whether a storage asset is even eligible equipment under this measure is itself unsettled at the outline stage. There is no settled view from the authorities as of June 2026, and whether immediate depreciation is available moves equity IRR by roughly ±1–3 points. A prior ruling request to METI and the National Tax Agency is the premise. The measure itself is at the FY2026 tax-reform-outline stage — a policy decision — and the text and entry into force are not yet complete.

JC-STAR (security certification) — the battery itself is out of scope. What is certified is the communications and control layer (IP communications equipment such as PCS, EMS and gateways); the battery cells and packs themselves are out of scope. Adopting foreign-made cells does not, in itself, run into a constraint. EHV and HV are slated for April 2027, and a working group has agreed on making the trigger the "grid-connection-contract application," though the text of the grid interconnection rules and the like is not yet promulgated. The fact that the trigger is the "application," not the "interconnection date," binds procurement and EPC schedules earlier, so deals aiming for an in-year interconnection need to confirm this sooner.

11 — Hold the risk in numbers

RiskWhat it isBiteWhen
Fee / creditToll-fee level, dependence on offtaker creditFee −10% cuts equity IRR several pointsNegotiation / operation
Balancing reformCap ¥19.51 → ¥15 (≈−23%), volume to 1σ (in force)Merchant unit revenue down ≈23% + volume downFrom March 2026
LDA award24% win rate, 6h raises CAPEX, 30% per-country cell capNo award / DSCR <1 at realistic prices = not viableAt bid
Tech / degradation≈1%/yr, 4h at start → 3h at end, SOH guaranteeCapacity decline cuts revenue; augmentation worsens DSCRYears 5–15
AccountingNew lease accounting (mandatory April 2027)On-balance-sheet for offtaker → affects appetiteFrom April 2027
FEFTA / FXCore-sector screening delay, FX on repatriationScreening delay delays interconnection / FX erodes returnBefore investment / at dividend
🚩 Tax"Lease use" exclusion from immediate depreciation (no authority view)Immediate depreciation availability moves equity IRR ±1–3ptAt acquisition / placing in service

Closing — Choose by the numbers, not the contract's name

The first question an investor should put in Japan is not "can we do a long-term PPA." Storage has no PPA. The questions to ask are: which of merchant, tolling, floor or LDA; over how many years; at what price; and who is the counterparty. Without fixing, even a public estimate is in the red; with fixing, leverage lifts the equity. Investment judgement begins by confirming that structure not by the contract's name, but by the numbers. And for an investor coming from the US, the UK or the EU, the toolkit is the one you already know — the work is reading it through Japan's prices, Japan's counterparties and Japan's gates.

Principal primary sources (as of June 2026)

Note: the amounts and returns in this piece are stated-assumption generic examples and public estimates, not the confirmed economics or contract terms of any actual deal. Domestic bilateral contract (toll / offtake / floor) unit prices and LDA storage-specific clearings are undisclosed. Points touching the interpretation of tax, FEFTA and accounting are not settled views from the authorities; individual deals require prior confirmation from tax advisers, lawyers and specialists.

Confirmed numbers from real deals, for your investment decision

This piece is a map of generic examples and public estimates. The confirmed CAPEX, toll fee, equity IRR, contract terms, FEFTA schedule and DD materials for real deals are
shared individually after you contact us and an NDA is in place. We work in English, Japanese and Chinese.

Contact us →