In three lines
  1. Only one company can bid a given battery.
  2. How to change that company is written neither in the exchange’s rules nor in its 704-page guide.
  3. During a switch there may be a period with no bidding in the balancing market. So write the exit into the first contract.

“How long does it take to switch?” Today, no public material answers that in days.

In this article
Three terms first What the search for “transfer” found What a switch looks like Only one published example gives a duration Five things to write into the first contract Or split between two from the start Thinking of switching? Whom to ask, in order How to read this series Frequently asked questions

Three terms first

Reading the exchange’s rules takes three terms: resource, list pattern and performance check.

Figure 1 A battery is registered in a bidding unit (a “list pattern”), and only one company bids it EPRX’s terms. Switching means changing the trading member at the right-hand end 1 Resource Each battery or other unit 2 Bidding unit EPRX calls it a “list pattern”: resources registered as a set 3 Trading member The company that bids the set. One per resource
Figure 1 What is registered as the bidding unit is the set that contains the battery. Change the company, and registration and checking are needed on the new company’s side (our reading).
  1. Resource. Each individual unit, such as a battery.
  2. List pattern. A set of resources registered with the exchange. Bids are placed by this unit.
  3. Performance check. The examination that confirms, from data and tests, that the set can respond as the product requires.

What the search for “transfer” found

An owner changes its aggregator. Seen from the exchange, that means the trading member bidding the battery changes. We searched the exchange’s documents for the procedure.

Figure 2 Searching for the “transfer” procedure We searched EPRX’s documents for “transfer”, “succession”, “change of name” and “change of trading member” (23 November 2026) Trading Rules (1 July 2026) 0 hits the terms do not appear Trading Guide (704 pages) 0 hits the terms do not appear Process flow (70 pages) 0 hits the terms do not appear FAQ 1 hit “a procedure is needed”; no documents, time or cost Model contract, Article 26 other about mergers and business transfers, not switching
Figure 2 No document sets out the transfer steps. The FAQ says, in one place, only that a transfer procedure is needed.

EPRX’s FAQ says this: two companies cannot bid the same battery, and for another company to use it, a transfer procedure is needed. What that procedure consists of is written nowhere.

Article 26 of the model contract does deal with “succession to the contract”. But it covers company mergers and business transfers, not the steps for an owner changing its operator.

What a switch looks like

Figure 3 Switching may bring a period with no bidding The sequence as we read it from the Rules, Guide, process flow and FAQ. The exchange gives no total in days No bidding in the balancing market during this period 1 Talk to the current one Check exit terms in the contract 2 New one registers after the transfer as its own resource 3 Performance check Within three months of data, as a rule 4 Bidding resumes Back in the market under the new name How many days: not stated in the exchange’s documents
Figure 3 A battery under examination cannot be bid in the balancing market. The performance check is to be done “within three months as a rule”.

Until the new aggregator’s registration goes through, balancing-market revenue may stop. How long, in our view, depends on whether test results can be carried over. Confirm with both the current and the new aggregator beforehand.

Table 1 gathers what is written.

Table 1 | Rules that bear on switching (from EPRX’s documents)
RuleContentWhere
One company per batteryTwo trading members cannot bid the same resourceFAQ
For another company to use itA transfer procedure is needed; what it consists of is not writtenFAQ
No bidding while under examinationA list pattern under examination cannot be bidFAQ
Performance check within three months as a ruleFrom acceptance of the application under the Trading Rules; from the day after the performance data is received under the process flowTrading Rules; process flow annexed to the Trading Guide
Tests can sometimes be skippedIf the live-test results of each resource are known, a list pattern made up of them can skip the live testTrading Guide, p. 127

The highlighted row is the one that bears on revenue: until the new company’s registration and check are complete, the battery may be unable to bid in the balancing market.

The wholesale and capacity markets are separate procedures. Moving a capacity-market contract needs OCCTO’s prior consent (Capacity Reservation Contract Terms, Article 26).

Only one published example gives a duration

From the decision to switch~3 months at bestTensor Energy’s switching support (subject to conditions; announced September 2026)

It covers high-voltage plants of 1 MW or more that are already operating, and only those using EMS from makers Tensor Energy has connected to or plans to connect to. This is one company’s announcement; it does not mean every switch takes three months. That this is the only yardstick is itself where things stand.

Five things to write into the first contract

With no published procedure, the contract is what an owner can rely on. So that a switch does not leave you stuck, write the exit into the first contract.

  1. The term, and the conditions for ending early. How many months’ notice? Is there a termination fee? The longer the contract, the more the terms for ending early matter.
  2. Cooperation on exit. The current aggregator helps with registration changes and hands over test results and data. This matters because, in our view, the length of any stoppage depends on whether test results can be carried over.
  3. Who owns the equipment and communications. Whose are the control devices and lines? Can they be used after a change? If they belong to the aggregator, they have to be replaced when you change.
  4. When results are reviewed. Results checked every six or twelve months, with a right to end the contract if they fall short of a benchmark. Set the benchmark in a form that can be compared with outside numbers, such as the market average.
  5. The name in each market. In whose name the plant is registered or contracted in the balancing, wholesale and capacity markets. Where the name is the aggregator’s, a transfer procedure is needed market by market.

Fees and contract structures are covered in COLUMN 17.

Or split between two from the start

Figure 4 Split between two from the start, and you can compare without switching An approach for owners with several plants (illustration) Everything with one Plant 1 Plant 2 Plant 3 Plant 4 Aggregator A ○ Less work × Nothing to compare results with Split between two Plant 1 Plant 2 Plant 3 Plant 4 Aggregator A Aggregator B ○ Results side by side × Smaller volume each; more integration work
Figure 4 Blue Sky Energy in Japan and Kyon Energy in Germany have said publicly that they use more than one operator.

If you own several plants, dividing them lets you compare results without switching. In April 2026 Blue Sky Energy announced this policy as its “multi-aggregator strategy”.

As the ○ and × in the figure show, splitting has its costs: each company runs less, and there are more systems to connect. Even so, in our view, being able to see results side by side is one of the few yardsticks an owner has in Japan, where there is no league table.

Thinking of switching? Whom to ask, in order

Before raising termination, ask three parties, in this order.

Table 2 | Whom to ask, and what
WhomWhat to ask
1. The current aggregatorExit terms and any termination fee. Whether test results and data will be handed to the new company. Who owns the control devices and lines
2. The new aggregatorWhether it can connect to the existing control system (EMS) and lines. Whether the performance check has to be redone. When bidding is expected to resume. Whether it has done such a switch before
3. The exchange and the grid companyThe documents and time the transfer procedure takes, confirmed through the new company

Estimate the stoppage only once all three answers are in. Terminate before then, and there is no telling how long revenue will stop.

How to read this series

COLUMN 53
Overview
187 companies. Public data cannot name the best
COLUMN 53-2
The roster
Filing involves no test of skill. One in three is under a year old
COLUMN 53-3
Volumes
“1.5 GW” is a forecast. Check the stage of every figure
COLUMN 53-4
Pricing
The cap halved in a year. Three things now set operators apart
COLUMN 53-5
Overseas
Britain’s No. 1 in September ran 30 MW. League tables show the gap
COLUMN 53-6
Switching
The switching procedure is written nowhere
You are reading this one

Frequently asked questions

Can the aggregator of a grid-scale battery be changed part-way through?

The change itself is anticipated: EPRX’s FAQ says a transfer procedure is needed for another trading member to use a resource. But the Trading Rules, Trading Guide and process flow contain no transfer procedure, and the documents, duration and cost are not published.

How long does it take to switch aggregator?

Public material does not give a number of days. The performance check is made, as a rule, within three months of receipt of the application under the Trading Rules, and within three months from the day after the performance data are received under the process flow annexed to the Trading Guide. Among private companies there is one example: Tensor Energy announced “about three months at the shortest” for its switching support, subject to conditions.

Does revenue stop during a switch?

In the balancing market, there can be a period when it does. According to EPRX’s FAQ, a bidding unit under examination (what EPRX calls a “list pattern”) cannot be bid. The wholesale and capacity markets are separate procedures.

What should I do first if I want to change aggregator?

Check the exit terms and any termination fee in the current contract. Then ask the current aggregator whether test results and data will be handed to the new company, and who owns the control devices and lines. Ask the new aggregator whether it can connect to the existing equipment, whether the performance check must be redone, and when bidding is expected to resume.

Primary sources and related articles

Rules relevant to switching

Company announcements

Related articles

The big picture on this topic: EPRX and Japan's Balancing Market: A Guide →

Supervised by
— Representative Director, Science X Inc.

Written and supervised on the basis of our hands-on work on grid-scale battery storage project transactions. The company counts are our own count of the lists published by ANRE and EPRX. Volumes under management are as announced by each company. The classification by business type is our own, from published material, and is approximate; where we rely on press reports, the text or table says so. This English edition is a translation of the Japanese original; for legal and regulatory matters, the Japanese primary sources govern. To point out an error, write to s@scix.co.jp.