- Grid connection study (接続検討)
- The procedure in which the general transmission and distribution utility examines whether a project can be connected to the grid. The reply document states the connection conditions (connection point, construction cost contribution and construction period).
- Connection study reply (接続検討回答書)
- The reply document issued by the transmission and distribution utility that states the grid connection conditions. It is the core document of the development rights; both the contribution and the construction period are desk studies, not commitments. It expires one year after the reply.
- Notes document attached to the reply (注意事項説明書)
- A common form of OCCTO attached to the connection study reply. It shows that both the contribution and the construction period are desk studies and will move with the on-site surveys and land negotiations that follow the contract application.
- Check on whether a new study is needed (接続検討の要否確認)
- A procedure for confirming with the general transmission and distribution utility whether a new connection study is needed, when equipment such as the battery or the PCS is changed after the connection study reply has been received. It is applied for on an OCCTO form, the reply comes in principle within one month, and no study fee is charged. Changing equipment after the connection study reply →
- Contract application, final reply (契約申込み)
- The stage after the connection study. The final reply to the contract application fixes the construction cost contribution and moves the project up one stage.
- Construction cost contribution (工事費負担金)
- The part of the grid connection construction cost that the applicant bears. The amount differs by an order of magnitude depending on whether the connection point is a transmission line or a distribution line; it is fixed at the final reply, and in most cases the connection construction period is counted from the payment. Why connection costs differ tenfold →
- Connection approval, connection contract (連系承諾)
- Being granted connection on the basis of the final reply to the contract application. Some things are fixed, and some still move.
- Anti-slot-hoarding measures, the new rules of April 2026 (空押さえ対策)
- Measures taken in response to the sharp rise in the number of connection studies. From April 2026, an increase in the deposit and mandatory submission of proof of land title, among other things, began, and the gap widened between projects already developed and projects only now starting. New rules for connection studies and contract applications →
- Cap on connection studies (接続検討数の上限)
- From August 1, 2026, a cap on the number of connection studies for grid batteries per operator (those not yet replied to).
- Expected connection timing (連系の見込み)
- How our project list shows it. For projects with a decided start of operation it is shown by year and month; for projects without one, by the number of months until connection stated in the reply document.