- Of about 76 companies we checked, nine publish a volume as a number.
- The largest, “over 1.5 GW”, is a forecast to 2030. Only one company says it counts just the plants already operating.
- Before you sign, ask: “how many MW, at which stage?”
“Company A has 1,000 MW and Company B has 200 MW, so A has the better record, right?” Not necessarily.
First, MW and MWh
A battery’s size is stated in two numbers. MW (megawatts) is how much power it can deliver at once. MWh (megawatt-hours) is how much it can store.
When a company says how much it runs, the figure is usually in MW. 1 GW (gigawatt) is 1,000 MW. Some Japanese companies write in units of 10,000 kW, each equal to 10 MW: Tokyo Gas’s “1.076 million kW” is 1,076 MW.
The nine figures, side by side
The colour of each bar is the stage of the figure. Pale purple is expected or planned, dark purple is ordered, contracted or applied for, and green is in operation. Only one bar is green.
| Company | Figure | What it counts | Announced |
|---|---|---|---|
| E-Flow | over 1.5 GW | What it expects to be running, under contract to operate, by 2030 | 6 Nov 2026 |
| Tokyo Gas | 1,076 MW | Batteries it plans to operate | 15 Jul 2026 |
| Osaka Gas | over 300 MW | Scale of operation, including batteries beside renewable plants and projects already decided | 16 Nov 2026 |
| Digital Grid | 250 MW | Plants in operation (as of 4 November) | 5 Nov 2026 |
| Tensor Energy | 250 MW | Applications for low-voltage batteries | 7 Sep 2026 |
| Marubeni Power Retail | 179 MW | Orders received for operation | 13 Oct 2026 |
| ReENE Energy Management | about 165 MW | Operation it plans to take on for batteries developed by its group | 2 Nov 2026 |
| Power Pool | about 60 MW | What it plans to start operating within 2026 (plus about 14 MW it now monitors) | 10 Aug 2026 |
| NUVVE JAPAN | 6 MW | Contracted | 6 Jan 2026 |
The highlighted row is the one figure whose announcement says it counts only plants in operation.
We went through the news pages of about 76 companies. For 60 we read every item since January 2024; for 3 we read only part; for 13 there was no list or the site would not open. These nine published a number. Apart from the roughly 14 MW it now monitors, Power Pool states about 60 MW it plans to start operating within 2026. We do not count companies that publish only a figure combined with solar or wind power plants.
In an interview rather than an announcement, Toshiba said it has contracts for about 120 grid-scale battery sites so far (Nikkei xTECH, 14 October 2026). That yardstick is a count of sites.
Added up, about three times what is running in Japan
The nine figures add up to about 3,800 MW. Yet grid-scale batteries actually connected and running across Japan came to 1,280 MW at the end of June 2026 (ANRE; see our Japan BESS market overview). That is about 1.5 times the 840 MW at the end of March, three months earlier (COLUMN 47-3).
The dates and the counting differ. Even so, it is plain that most of the announced figures are still to come. The bigger the number, the more it matters to ask which stage it describes.
Every figure sits at one of four stages
“Expected” means plants not yet running, and can include some not even contracted. “Contracted” includes plants not yet built. Only from the third stage can you call it a track record.
| Stage | What is counted | What to watch |
|---|---|---|
| 1. Expected or planned | Plants to be run in future, including targets and plans | If connection or construction slips, the figure moves |
| 2. Ordered, contracted, applied for | Contracts signed and applications received | Includes plants not yet built |
| 3. In operation | Plants that have started running | Which markets they run in is a separate question |
| 4. Admitted to the market | Plants that have passed the tests and can bid in that market | The figure differs from market to market |
The figure shrinks as you move from 1 to 4. A large number is not a bad thing. Comparing figures at different stages is where the mistake lies.
One company, two numbers
Digital Grid published two figures in November 2026: 250 MW in operation (as of 4 November) and over 150 MW admitted to the balancing market (as of 19 November). How it counts is written in the chart note. Few companies say this much.
The 250 MW and the “over 150 MW” count different stages. A plant that has started running still has to pass the exchange’s checks before it can enter the balancing market.
When you read a figure, look beyond the body text to the notes on the charts. How it was counted is usually written there.
What the figure includes also changes it
The same MW can cover different things. If you are handing over a grid-scale plant, ask for the grid-scale figure alone.
| Content | What kind of battery | Example among the nine |
|---|---|---|
| Grid-scale batteries | Battery plants connected directly to the grid | The core of most companies’ figures |
| Co-located batteries | Batteries attached to solar and other power plants | Osaka Gas (includes co-located) |
| Low-voltage units | Small units under 50 kW, run together in large numbers (COLUMN 44) | Tensor Energy (low-voltage applications) |
| Group-owned batteries | Plants developed by the parent or the group | ReENE Energy Management |
Five things to ask before you sign
- Which stage is that MW? Expected, contracted, operating, or admitted to the market. A forecast and an operating plant carry very different weight as a record.
- What does it include? Grid-scale only, or also batteries beside solar plants and small low-voltage units? Ask for the figure for the same kind of plant as your own.
- How many MW excluding your own and your group’s plants? What it runs for outside owners is the record that matches your position.
- As of when? In 2026 the figures have moved a great deal within months. Ask for the date it was counted, not the date it was announced.
- Which markets? Which balancing-market products? What about the wholesale and capacity markets? What has been admitted to a market is what has passed the tests and can actually bid.
A company that can answer all five with numbers is easier to move forward with. Fees and contract structures are covered in COLUMN 17.
How to read this series
Frequently asked questions
Which aggregator runs the most grid-scale batteries in Japan?
Public material cannot settle it. Leaving targets aside, the largest announced figure is E-Flow’s “over 1.5 GW”, but that is what it expects to be operating by 2030. Tokyo Gas’s 1,076 MW is planned operation, Marubeni Power Retail’s 179 MW is orders received, and Digital Grid’s 250 MW is plants in operation. The yardsticks do not match, so no ranking is possible.
If I add up each company’s volume, do I get the total for Japan?
No. Expected, contracted and operating figures are mixed, and far more companies publish no figure at all.
Is a company with a larger volume the safer choice?
Size alone does not tell you. Look at how much is actually operating and how much is run for outside owners.
Primary sources and related articles
Company announcements
- E-Flow, announcement (6 November 2026, in Japanese)
- Tokyo Gas, press release (15 July 2026, in Japanese)
- Osaka Gas, press release (16 November 2026, in Japanese)
- Digital Grid, announcement that handled grid-scale battery volume passed 250 MW (5 November 2026; the chart note says “counted by start-of-operation date”, in Japanese)
- Digital Grid, announcement of over 150 MW admitted to the balancing market (20 November 2026, in Japanese)
- Marubeni Power Retail, announcement (13 October 2026, in Japanese)
- ReENE and Mitsubishi Electric, announcement (2 November 2026, in Japanese)
- Power Pool, announcement (10 August 2026, in Japanese)
- NUVVE JAPAN K.K., announcement (on Nuvve’s website, 6 January 2026)
- Tensor Energy, announcement (7 September 2026, in Japanese)
- Nikkei xTECH, interview with Toshiba on grid-scale batteries (14 October 2026, in Japanese)
- Shizen Connect, announcement (22 May 2026, in Japanese)