In three lines
  1. Of about 76 companies we checked, nine publish a volume as a number.
  2. The largest, “over 1.5 GW”, is a forecast to 2030. Only one company says it counts just the plants already operating.
  3. Before you sign, ask: “how many MW, at which stage?”

“Company A has 1,000 MW and Company B has 200 MW, so A has the better record, right?” Not necessarily.

In this article
First, MW and MWh The nine figures, side by side Added up, about three times what is running in Japan Every figure sits at one of four stages One company, two numbers What the figure includes also changes it Five things to ask before you sign How to read this series Frequently asked questions

First, MW and MWh

A battery’s size is stated in two numbers. MW (megawatts) is how much power it can deliver at once. MWh (megawatt-hours) is how much it can store.

Figure 1 MW is how much power at once; MWh is how much is stored A battery’s size is given by these two numbers. Company “volumes” are usually in MW MW (megawatt) Power delivered at once Like the width of a tap MWh (megawatt-hour) Energy held in store Like the size of the tank Example: a 2 MW / 8 MWh plant 8 MWh ÷ 2 MW = four hours of output 2MW 2MW 2MW 2MW 1 GW = 1,000 MW = 1,000,000 kW
Figure 1 A 2 MW / 8 MWh plant can deliver 2 MW for four hours. 1 GW is 1,000 MW.

When a company says how much it runs, the figure is usually in MW. 1 GW (gigawatt) is 1,000 MW. Some Japanese companies write in units of 10,000 kW, each equal to 10 MW: Tokyo Gas’s “1.076 million kW” is 1,076 MW.

The nine figures, side by side

Figure 2 Volumes announced by nine companies. Bars of different colours cannot be compared Company announcements (January–November 2026), converted to MW. Colour shows the stage each figure describes E-Flow over 1.5 GW (expected by 2030) Tokyo Gas 1,076 MW (planned) Osaka Gas over 300 MW (incl. renewables-paired and committed projects) Digital Grid 250 MW (operating) Tensor Energy 250 MW (low-voltage applications) Marubeni Power Retail 179 MW (orders) ReENE Energy Management about 165 MW (to be entrusted; group batteries) Power Pool about 60 MW (to start within 2026) NUVVE JAPAN 6 MW (contracted) Expected / planned Ordered / contracted / applied Operating
Figure 2 The longest bar is a forecast to 2030. Only Digital Grid’s 250 MW is stated to count plants already operating.

The colour of each bar is the stage of the figure. Pale purple is expected or planned, dark purple is ordered, contracted or applied for, and green is in operation. Only one bar is green.

Table 1 | The nine published figures and how each was described (checked by us against each announcement)
CompanyFigureWhat it countsAnnounced
E-Flowover 1.5 GWWhat it expects to be running, under contract to operate, by 20306 Nov 2026
Tokyo Gas1,076 MWBatteries it plans to operate15 Jul 2026
Osaka Gasover 300 MWScale of operation, including batteries beside renewable plants and projects already decided16 Nov 2026
Digital Grid250 MWPlants in operation (as of 4 November)5 Nov 2026
Tensor Energy250 MWApplications for low-voltage batteries7 Sep 2026
Marubeni Power Retail179 MWOrders received for operation13 Oct 2026
ReENE Energy Managementabout 165 MWOperation it plans to take on for batteries developed by its group2 Nov 2026
Power Poolabout 60 MWWhat it plans to start operating within 2026 (plus about 14 MW it now monitors)10 Aug 2026
NUVVE JAPAN6 MWContracted6 Jan 2026

The highlighted row is the one figure whose announcement says it counts only plants in operation.

We went through the news pages of about 76 companies. For 60 we read every item since January 2024; for 3 we read only part; for 13 there was no list or the site would not open. These nine published a number. Apart from the roughly 14 MW it now monitors, Power Pool states about 60 MW it plans to start operating within 2026. We do not count companies that publish only a figure combined with solar or wind power plants.

In an interview rather than an announcement, Toshiba said it has contracts for about 120 grid-scale battery sites so far (Nikkei xTECH, 14 October 2026). That yardstick is a count of sites.

Added up, about three times what is running in Japan

Figure 3 Add the nine figures and you get about three times what is running in Japan Top: sum of the nine announcements (Jan–Nov 2026). Bottom: grid-scale batteries connected and running in Japan (end of June 2026) Sum of the nine about 3,800 MW (stages mixed) Running in Japan 1,280 MW (end of June 2026)
Figure 3 The dates and the counting differ, so the ratio is only a rough guide. The nine figures also include renewables-paired plants and low-voltage applications. What it shows is that most of the announced figures are still to come.

The nine figures add up to about 3,800 MW. Yet grid-scale batteries actually connected and running across Japan came to 1,280 MW at the end of June 2026 (ANRE; see our Japan BESS market overview). That is about 1.5 times the 840 MW at the end of March, three months earlier (COLUMN 47-3).

The dates and the counting differ. Even so, it is plain that most of the announced figures are still to come. The bigger the number, the more it matters to ask which stage it describes.

Every figure sits at one of four stages

Figure 4 Every “MW” figure sits at one of four stages A battery plant moves through these in order before it earns. The figure shrinks as you go right 1 Expected Not yet running Slips if projects slip 2 Contracted Contract signed May not be built yet 3 In operation Plant is running Which market is separate 4 Admitted to the market Passed the tests Can bid
Figure 4 The question is not “how many MW?” but “how many MW, at which stage?”

“Expected” means plants not yet running, and can include some not even contracted. “Contracted” includes plants not yet built. Only from the third stage can you call it a track record.

Table 2 | The four stages of a volume figure
StageWhat is countedWhat to watch
1. Expected or plannedPlants to be run in future, including targets and plansIf connection or construction slips, the figure moves
2. Ordered, contracted, applied forContracts signed and applications receivedIncludes plants not yet built
3. In operationPlants that have started runningWhich markets they run in is a separate question
4. Admitted to the marketPlants that have passed the tests and can bid in that marketThe figure differs from market to market

The figure shrinks as you move from 1 to 4. A large number is not a bad thing. Comparing figures at different stages is where the mistake lies.

One company, two numbers

Figure 5 Counting only plants in operation, this is the growth (Digital Grid) From the chart in its announcement (5 November 2026), in MW. The note says the count is by start-of-operation date 4 Jan 2025 6 Apr 10 Jul 24 Oct 62 Jan 2026 102 Apr 165 Jul 207 Sep 250 Nov 383 Jul 2028 (plan) ≈
Figure 5 From 62 MW in January 2026 to 250 MW in November: fourfold in ten months. The dashed bar is its plan for July 2028. The gap between November 2026 and July 2028 is skipped, as in its chart.

Digital Grid published two figures in November 2026: 250 MW in operation (as of 4 November) and over 150 MW admitted to the balancing market (as of 19 November). How it counts is written in the chart note. Few companies say this much.

The 250 MW and the “over 150 MW” count different stages. A plant that has started running still has to pass the exchange’s checks before it can enter the balancing market.

When you read a figure, look beyond the body text to the notes on the charts. How it was counted is usually written there.

Look inside “No. 1 share” as well. Shizen Connect’s “about 26%” (announced May 2026) comes from a Fuji Keizai survey and counts corporate contracts for operation-and-control systems (AC and RA systems), as estimated for fiscal 2025. It is not a share of grid-scale battery MW.

What the figure includes also changes it

The same MW can cover different things. If you are handing over a grid-scale plant, ask for the grid-scale figure alone.

Table 3 | What a figure may include
ContentWhat kind of batteryExample among the nine
Grid-scale batteriesBattery plants connected directly to the gridThe core of most companies’ figures
Co-located batteriesBatteries attached to solar and other power plantsOsaka Gas (includes co-located)
Low-voltage unitsSmall units under 50 kW, run together in large numbers (COLUMN 44)Tensor Energy (low-voltage applications)
Group-owned batteriesPlants developed by the parent or the groupReENE Energy Management

Five things to ask before you sign

  1. Which stage is that MW? Expected, contracted, operating, or admitted to the market. A forecast and an operating plant carry very different weight as a record.
  2. What does it include? Grid-scale only, or also batteries beside solar plants and small low-voltage units? Ask for the figure for the same kind of plant as your own.
  3. How many MW excluding your own and your group’s plants? What it runs for outside owners is the record that matches your position.
  4. As of when? In 2026 the figures have moved a great deal within months. Ask for the date it was counted, not the date it was announced.
  5. Which markets? Which balancing-market products? What about the wholesale and capacity markets? What has been admitted to a market is what has passed the tests and can actually bid.

A company that can answer all five with numbers is easier to move forward with. Fees and contract structures are covered in COLUMN 17.

How to read this series

COLUMN 53
Overview
187 companies. Public data cannot name the best
COLUMN 53-2
The roster
Filing involves no test of skill. One in three is under a year old
COLUMN 53-3
Volumes
“1.5 GW” is a forecast. Check the stage of every figure
You are reading this one
COLUMN 53-4
Pricing
The cap halved in a year. Three things now set operators apart
COLUMN 53-5
Overseas
Britain’s No. 1 in September ran 30 MW. League tables show the gap
COLUMN 53-6
Switching
The switching procedure is written nowhere

Frequently asked questions

Which aggregator runs the most grid-scale batteries in Japan?

Public material cannot settle it. Leaving targets aside, the largest announced figure is E-Flow’s “over 1.5 GW”, but that is what it expects to be operating by 2030. Tokyo Gas’s 1,076 MW is planned operation, Marubeni Power Retail’s 179 MW is orders received, and Digital Grid’s 250 MW is plants in operation. The yardsticks do not match, so no ranking is possible.

If I add up each company’s volume, do I get the total for Japan?

No. Expected, contracted and operating figures are mixed, and far more companies publish no figure at all.

Is a company with a larger volume the safer choice?

Size alone does not tell you. Look at how much is actually operating and how much is run for outside owners.

Primary sources and related articles

Company announcements

Related articles

The big picture on this topic: EPRX and Japan's Balancing Market: A Guide →

Supervised by
— Representative Director, Science X Inc.

Written and supervised on the basis of our hands-on work on grid-scale battery storage project transactions. The company counts are our own count of the lists published by ANRE and EPRX. Volumes under management are as announced by each company. The classification by business type is our own, from published material, and is approximate; where we rely on press reports, the text or table says so. This English edition is a translation of the Japanese original; for legal and regulatory matters, the Japanese primary sources govern. To point out an error, write to s@scix.co.jp.