The 280 projects we list, counted by grid area, prefecture, voltage class, structure, status, size and expected grid connection: where the projects are, when they are expected to connect, and how many can be bought as development rights or as completed-build handovers. As of . The tables are also available as CSV (Japanese).
These are the battery storage projects for sale that have been brought to ScienceX and cleared for listing, all with a grid connection study answer from the utility. They are ScienceX’s own listings, not statistics for the whole Japanese market. Sites and sellers are not published (prices and documents are on Chikudensho Market after free registration). The figures are recounted every morning from the same data as the project list.
Grid area = the service area of the general transmission and distribution operator.
| Grid area | Projects | Total MW |
|---|---|---|
| Tokyo | 65 | 168 |
| Chubu | 59 | 436 |
| Kyushu | 88 | 927 |
| Kansai | 24 | 199 |
| Chugoku | 15 | 175 |
| Tohoku | 22 | 250 |
| Hokkaido | 3 | 34 |
| Hokuriku | 3 | 6 |
| Shikoku | 1 | 2 |
There are projects in 38 prefectures.
| Prefecture | Projects |
|---|---|
| Kagoshima | 30 |
| Shizuoka | 22 |
| Saitama | 20 |
| Kumamoto | 18 |
| Gifu | 17 |
| Tochigi | 15 |
| Miyazaki | 13 |
| Saga | 11 |
| Fukuoka | 10 |
| Fukushima | 9 |
High-voltage projects are mostly around 2 MW; extra-high-voltage projects are roughly 10 MW and above. A project is sold either as development rights that the buyer builds out (transfer of rights) or as a completed-build handover. Status shows whether the utility has answered the grid connection study, whether the grid construction cost has been fixed, or whether the project is already connected.
For each voltage class, how many projects are sold as development rights (the buyer builds) and how many as completed-build handovers. Of 231 high-voltage projects, 186 are completed-build handovers; of 46 extra-high-voltage projects, 43 are transfers of rights.
| Voltage class | Transfer of rights | Completed-build handover | Under review | Total |
|---|---|---|---|---|
| High voltage | 43 | 186 | 2 | 231 |
| Extra-high voltage | 43 | 2 | 1 | 46 |
| Other | 3 | 0 | 0 | 3 |
| Total | 89 | 188 | 3 | 280 |
All 280 projects are counted. Voltage classes with fewer than 5 projects (Low voltage) are combined as “Other”. “Under review” means the structure is not yet fixed.
The 239 projects with a capacity value, grouped by size (41 of the 280 projects have no value and are not counted). Median size: high voltage 2 MW (195 projects); extra-high voltage 37.5 MW (44 projects).
Shares are of the 239 projects with a value. Medians are shown only for voltage classes with at least 5 projects.
Projects with a planned operation date are counted by Japanese fiscal half-year (the fiscal year starts in April); the others by the months to connection stated in the grid connection study answer. 111 projects have a planned date, 119 have no planned date but a stated number of months, and 45 are under review. In all, 153 projects (including some with a planned date) have a stated number of months; the “Months to connection” chart counts these 153.
The 153 projects whose grid connection study answer states the months needed to connect, counted by structure (127 of the 280 projects have no figure and are not counted). By voltage class, the median is high voltage 12 months (123 projects); extra-high voltage 31.5 months (30 projects).
| Structure | Projects with a figure | Median | Within 6 months | 7–12 months | 13–24 months | 25 months or more |
|---|---|---|---|---|---|---|
| Transfer of rights | 61 | 24 months | 5 | 10 | 17 | 29 |
| Completed-build handover | 91 | 12 months | 18 | 29 | 38 | 6 |
The months are as written in the utility’s answer; 17 of them state a start point (such as payment of the grid construction cost). These are not months from the planned commercial operation date. Structures with fewer than 5 figures (1 project) are not shown.
Number and total capacity of the projects visible to buyers at the end of each week (Monday-start weeks, last 12). The latest week is partial, as of 2026-11-23.
High voltageExtra-high voltage
| Week of | Projects | Total MW | High voltage | Extra-high | Transfer of rights | Completed-build | New listings |
|---|---|---|---|---|---|---|---|
| 124 | 1,386 | 104 | 20 | 33 | 90 | 5 | |
| 128 | 1,391 | 111 | 17 | 33 | 94 | 9 | |
| 124 | 1,293 | 109 | 15 | 30 | 93 | 6 | |
| 129 | 1,283 | 113 | 16 | 35 | 94 | 10 | |
| 134 | 1,330 | 117 | 17 | 36 | 96 | 12 | |
| 133 | 1,376 | 115 | 18 | 38 | 93 | 3 | |
| 153 | — | 133 | 17 | 45 | 104 | 30 | |
| 177 | — | 150 | 24 | 55 | 113 | 26 | |
| 229 | — | 206 | 20 | 52 | 168 | 67 | |
| 243 | — | 219 | 21 | 65 | 169 | 31 | |
| 279 | — | 230 | 46 | 89 | 187 | 53 | |
| (partial) | 280 | — | 231 | 46 | 89 | 188 | 1 |
The chart stacks high voltage and extra-high voltage; projects without a voltage (3 in the latest week) are not in the chart but are in the table counts. Total MW is shown as “—” for weeks when many projects had no capacity value, so that gaps in the data are not read as a change in market size. Growth in the number of listings reflects when we added projects to the list (some were added in batches), not growth of the market. ScienceX’s own listings, not statistics for the whole Japanese market. Projects whose structure is under review are not in the last two structure columns. No prices, sites or names are published here.
Projects now listed, by the month they were first listed. Projects taken off the list are not included. Growth in the number of listings reflects when we added projects to the list (some were added in batches), not growth of the market.
| Month first listed | Projects |
|---|---|
| 36 | |
| 21 | |
| 24 | |
| 62 | |
| 137 |
The conditions in the 12 buyer requests now listed on Chikudensho Market (conditions that buyers post for projects they want to buy), counted by option.
With only 12 requests, no trend over time is shown, and neither the buyers’ company profiles nor the dates posted are published. A request may name several grid areas, so area counts can add up to more than 12; shares are of the 12 requests. Options chosen fewer than 3 times are combined as “Other options”; requests that leave a field blank are “Not specified”. Recounted every morning from the public list on Chikudensho Market (counts last changed: ).
The tables on this page are also available as CSV (UTF-8 with BOM), rebuilt every morning from the same data. No prices, project names or sites are included.
You are welcome to quote the figures and charts on this page. Please give the source as follows.
Source: Science X Inc., “Grid-scale battery storage projects for sale in Japan: market data” (updated 2026-11-23), https://www.scix.co.jp/en/market-data
The full project list in English is on Projects; market prices (JEPX, capacity market) are on Battery Storage Market Data.
Current listings can be browsed on Chikudensho Market without registering. Prices and documents are shown after free registration, where you agree to a confidentiality undertaking on the registration screen (no signed paper is needed).