A battery storage site (grid-scale battery storage) earns income from three markets.
Apr 2026–Oct 2026 · from 7 issues · latest: Oct 2026 issue
In Oct 2026, the JEPX monthly average for System (nationwide) was 22.51 yen/kWh and the 4-hour spread was 20.42 yen/kWh (source: JEPX spot market).
Wholesale electricity is the electricity that power companies and retailers buy and sell. Its price is set in the "spot market" of the Japan Electric Power Exchange (JEPX) (the market where electricity for the next day is traded the day before). "System (nationwide)" is the price when all of Japan is treated as one market (the system price). When transmission lines between regions get congested, prices split by area from Hokkaido to Kyushu (area prices).
Definitions
Average prices are simple averages of 30-minute slots (not weighted by trading volume). Daytime is the slots from 8:00 to 16:00, and evening is the slots from 16:00 to 20:00.
Spread: we sort the day's 30-minute slots by price and subtract the average of the 8 cheapest slots from the average of the 8 most expensive slots (4 hours) (4 slots for 2 hours). We do not consider the order of cheap and expensive hours, electricity lost in charging and discharging, or fees, taxes and transmission charges. It does not show actual revenue.
Source: Spot market trading results published by the Japan Electric Power Exchange (JEPX). Prices are simple averages of 30-minute slots. Our totals. JEPX spot market
Source: JEPX spot market. Our totals. JEPX spot market
| Area | Monthly average | Same month last year | Daytime (8:00–16:00) | Evening (16:00–20:00) | 4-hour spread | Highest | Slots at 30 yen or more | Slots at 0.01 yen | 2-hour spread | Days with a 4-hour spread of 10 yen or more |
|---|---|---|---|---|---|---|---|---|---|---|
| System (nationwide) | 22.51 | 11.67 | 16.02 | 31.06 | 20.42 | 47.88 | 220 | 39 | 22.95 | 29 |
| Hokkaido | 20.49 | 12.89 | 11.31 | 32.25 | 29.02 | 105.00 | 303 | 67 | 32.56 | 31 |
| Tohoku | 23.99 | 12.08 | 15.78 | 34.19 | 24.74 | 50.01 | 437 | 95 | 27.09 | 30 |
| Tokyo | 27.02 | 13.06 | 23.12 | 34.69 | 17.14 | 50.01 | 466 | 16 | 19.62 | 29 |
| Chubu | 25.46 | 11.68 | 20.38 | 33.55 | 19.91 | 46.45 | 387 | 24 | 22.37 | 29 |
| Hokuriku | 19.70 | 11.27 | 18.29 | 26.92 | 19.18 | 46.45 | 218 | 24 | 21.71 | 31 |
| Kansai | 19.50 | 11.27 | 18.22 | 26.76 | 18.71 | 46.45 | 215 | 29 | 21.22 | 31 |
| Chugoku | 15.63 | 11.12 | 9.86 | 23.10 | 18.93 | 44.79 | 63 | 79 | 20.90 | 31 |
| Shikoku | 11.44 | 9.28 | 7.50 | 16.61 | 17.27 | 37.51 | 23 | 146 | 19.40 | 28 |
| Kyushu | 15.07 | 10.74 | 8.31 | 23.10 | 19.30 | 44.79 | 53 | 91 | 21.19 | 31 |
Issue: Oct 2026 issue
Download CSV (month × area, all measures)For FY2029, the main auction area price was highest in Kyushu at 15,112 yen/kW per year and lowest in Chubu at 12,388 yen/kW per year (source: OCCTO).
The capacity market buys electricity supply capacity four years ahead through an auction held once a year.
| Delivery fiscal year | Hokkaido | Tohoku | Tokyo | Chubu | Hokuriku | Kansai | Chugoku | Shikoku | Kyushu |
|---|---|---|---|---|---|---|---|---|---|
| FY2024 | 14,137 | 14,137 | 14,137 | 14,137 | 14,137 | 14,137 | 14,137 | 14,137 | 14,137 |
| FY2025 | 5,242 | 3,495 | 3,495 | 3,495 | 3,495 | 3,495 | 3,495 | 3,495 | 5,242 |
| FY2026 | 8,749 | 5,833 | 5,834 | 5,832 | 5,832 | 5,832 | 5,832 | 5,832 | 8,748 |
| FY2027 | 13,287 | 9,044 | 9,555 | 7,823 | 7,638 | 7,638 | 7,638 | 7,638 | 11,457 |
| FY2028 | 14,812 | 14,812 | 14,812 | 10,280 | 8,785 | 8,785 | 8,785 | 8,785 | 13,177 |
| FY2029 | 14,972 | 15,111 | 15,111 | 12,388 | 12,388 | 12,388 | 12,388 | 12,388 | 15,112 |
Source: Clearing results and capacity contract documents published by the Organization for Cross-regional Coordination of Transmission Operators (OCCTO). As published. 2024 2025 2026 2027 2028 2029
Capacity market clearing results for each delivery fiscal year are published in a different year (results for FY2024 in 2020, for FY2029 in January 2026). We do not show the number of battery projects in the Long-Term Decarbonization Power Source Auction, because it is not in the published summary tables.
Long-Term Decarbonization Power Source Auction a separate auction that promises capacity income, in principle for 20 years, for things like building new decarbonized power sources
| Auction fiscal year | Category | Contracted capacity (10,000 kW) |
|---|---|---|
| FY2023 auction | Battery storage and pumped hydro | 166.9 |
| FY2024 auction | Duration of 3 hours to under 6 hours | 96.1 |
| FY2024 auction | Duration of 6 hours or more | 76.9 |
| FY2025 auction | Lithium-ion battery storage and pumped hydro (excluding new builds) | 81.9 |
| FY2025 auction | Non-lithium-ion battery storage, pumped hydro (new builds) and LDES | 88.6 |
Source: Clearing results and capacity contract documents published by the Organization for Cross-regional Coordination of Transmission Operators (OCCTO). As published. 2023 2024 2025
Issue: Oct 2026 issue
Download CSV (contracted capacity)The balancing market is where grid operators buy the "power" to fix electricity surpluses and shortages every 30 minutes.
Bid ratios, award rates and average winning prices by product are in the "Market numbers" section of each issue:
You are welcome to quote the figures and charts on this page. Please give the source as follows.
Source: Science X Inc., “Battery Storage Market Data” (updated 2026-11-22), https://www.scix.co.jp/en/report/data
The figures are tallies of published data and our own records. The price spread is a difference in price per kWh and does not show actual revenue. CSV downloads are below each section; the reuse terms are in the citation guide.