In three lines
  1. Whether ★1 is needed depends on the day the grid operator accepted the contract application. It is 1 April 2027 for extra-high and high voltage, and 1 October for low voltage.
  2. The requirement does not apply retroactively to existing plants. If you add a battery to an existing solar plant, ★1 is needed only for the added devices.
  3. When you replace a device, the new device generally needs ★1. Only in cases of "excessive burden", such as having to replace other devices too, can you submit a plan and get a grace period.

"Our solar plant was connected in 2019. If we add a battery next to it, do we have to replace the solar PCS too?" This is the first question that comes up when a battery is added to an existing solar plant.

In June 2026, when we wrote COLUMN 14, the materials did not say how this was treated. In July, ANRE answered in its FAQ. In October, the draft revision put it into the text. This article sets the line out in one diagram and one table.

In this article
The starting point is the acceptance date of the contract application Terms used in this series The diagram No retroactive application If you add, only the added side A replaced device generally needs ★1 Low voltage is October because of stock in distribution Schemes that already require ★1 What to check before you buy How to read this series FAQ

The starting point is the acceptance date of the contract application

Whether ★1 is needed depends on the day the grid operator accepted the contract application. It applies to projects accepted on or after 1 April 2027 for extra-high and high voltage, and on or after 1 October 2027 for low voltage.

"Acceptance" is the point when the application documents are complete and the deposit has been paid. It is not enough to have applied for a connection study or received its reply.

Merely having a connection study application accepted does not secure the previous treatment. The previous treatment applies only if you file a contract application on the basis of the study result and the grid operator has accepted that contract application.ANRE, "Frequently asked questions", A2 (our translation)

If your project has "filed the contract application, but the deposit is still to come", the acceptance date could fall after April 2027. Check the date first.

This is not final yet. The public comment period on the draft revision ran from 6 October to 6 November 2026 (e-Gov case no. 620340012). The revised texts of the 10 grid operators have not been published. This article is based on the draft revision and ANRE's FAQ.

Terms used in this series

This series uses the terms below. All four articles share the same table.

Table 0 | Terms used in this series (quick reference)
TermMeaning
JC-STARA security labelling scheme for devices connected to the internet (IoT devices). METI launched it in March 2025. The Information-technology Promotion Agency, Japan (IPA) runs it.
★1 (Level 1)The lowest level. The maker checks the basic rules itself and applies. The rules include no default passwords, a contact point for faults, and software that can be fixed. Third-party assessment applies only at ★3 and ★4.
PCS (power conditioning system)The machine that changes the form of electricity between the battery (DC) and the grid (AC). It is the heart of a storage site.
BMSThe battery management system. It watches the temperature and voltage of the battery.
EMSThe energy management system. It decides when to charge and when to discharge.
Remote monitoring / gatewayThe front door that connects a power plant or storage site to outside networks.
The grid / grid connectionThe grid means the transmission and distribution lines of the power companies. Connecting a power plant or storage site to it is called grid connection.
Grid operator (general transmission and distribution operator)The transmission and distribution companies of the large power utilities. There are 10 across Japan, such as Tokyo Electric Power Grid.
Connection studyA procedure in which the grid operator checks whether a site can connect and how much the works will cost. It comes before the contract application.
Contract applicationThe formal application filed after the connection study reply. It counts as accepted only when the documents are complete and the deposit has been paid.
Extra-high voltage, high voltage, low voltageThe voltage classes of the connection. High voltage is roughly under 2,000 kW and low voltage is under 50 kW. Extra-high voltage is larger than both.

The diagram

Figure 1 shows the flow of which devices in which projects need ★1. Follow it from the top.

Fig. 1 Which projects, and which devices, need JC-STAR ★1 Our summary of the draft revised grid-connection guideline (Oct 2026) and ANRE's FAQ When did the grid operator accept the contract application? (complete documents, and the deposit paid) Extra-high / high voltage: on or after 1 Apr 2027? Low voltage (<50 kW): on or after 1 Oct 2027? No Existing rules apply ★1 is not required. A connection study alone does not count Yes What kind of application? 1 New build (solar / storage) All networked control devices need ★1 PCS, BMS, EMS, remote monitoring, gateways (devices with IP comms) Already required elsewhere The long-term decarbonisation auction and the national subsidy require ★1 at bid / application 2 Adding storage to an existing solar plant Only the added storage side needs ★1 The existing solar PCS and monitoring need nothing if left unchanged Depends on the wiring (our reading) AC-coupled (existing PCS kept): storage side only DC-coupled with a new PCS: the new PCS too → confirm in writing with the grid operator first 3 Replacing existing equipment (e.g. failure) The replacement device needs ★1, in principle Even a like-for-like swap needs a connection study Devices not replaced are out of scope Exception: an “excessive burden” Only where, e.g., one swap would force wider replacement: consult the grid operator and file a plan (1) why ★1 is not possible (2) when all devices will be ★1 (3) interim measures. If approved, a non-★1 device of the same type may be used Projects whose contract application was accepted by the end of March 2027 are not caught retroactively. The requirement reads: devices bearing a conformance label of ★1 or above under IPA's labelling scheme. The draft was open for public comment from 6 Oct to 6 Nov 2026; the ten grid operators' revised rules are not yet published.

No retroactive application

The draft says the requirement is "not applied retroactively" to projects whose acceptance is complete. This holds even if the equipment has not yet been built.

Even if the equipment has not yet been installed, this requirement shall not apply retroactively to a project for which acceptance of the contract application for the power generation equipment is complete.Guideline on Technical Requirements for Grid Interconnection, draft revision, Chapter 2, Section 1, 5 (1) (October 2026) (our translation)

A solar plant connected in 2019 is unaffected as long as it is used as it is.

But even for a project whose acceptance is complete, replacing the PCS or other devices with different ones after April 2027 requires an application for a change to the equipment. The requirement at that time then applies, so the replaced devices need ★1 (FAQ A3).

If you add, only the added side

When you add a battery to an existing solar plant, ★1 is needed for the devices on the added battery side. These are the PCS, BMS, EMS, remote monitoring unit, gateway and so on. The existing solar PCS and monitoring unit need nothing if they are not replaced.

For the covered devices used in an added battery, please use JC-STAR ★1 certified products.ANRE, "Frequently asked questions", A10 (our translation)

Switching from FIT to FIP and the end of the FIT period are not covered either, as long as no equipment is added or changed. If you add a battery at the same time as switching to FIP, only the added battery needs ★1. Even a fully self-consumed plant, which sends no power out, is covered if it is connected to the grid.

The devices covered change with the way the system is connected. Table 1 lists, for each configuration, the devices that need ★1 and the basis. The two DC-coupled rows are not described directly in the materials. They are our reading.

Table 1 | Configurations, and the devices that need ★1
ConfigurationDevices that need ★1Basis
A new buildAll control devices connected to the internet (PCS, BMS, EMS, remote monitoring, gateway and so on)Draft 5 (1)
Adding a battery to an existing solar plant (AC-coupled; the current PCS stays)PCS, BMS, EMS and gateway on the added battery sideFAQ A10
Adding a battery to an existing solar plant (DC-coupled; the PCS is replaced with a type that can also serve the battery)The replaced PCS, and the devices on the added battery side"Replacement" in draft 5 (2). Our reading
Adding a battery to an existing solar plant (DC-coupled; the current PCS stays, and a battery and BMS are added on the DC side)The devices on the added battery sideOur reading
Replacing a device, for example after a failureThe replaced device (in principle). Devices that are not replaced are not coveredDraft 5 (2), FAQ A11
Switching from FIT to FIP, or the end of the FIT period (no change to equipment)Not neededFAQ
Adding a battery at the same time as switching to FIP or the end of the FIT periodOnly the added battery sideFAQ A12
Fully self-consumed (no export)Same as the others if connected to the gridFAQ A13

The treatment of DC-coupled systems is not described directly in the materials. Before you rely on it, confirm it in writing with the local grid operator.

A replaced device generally needs ★1

When you replace one PCS after a failure, that one is in principle required to have ★1. Devices you do not replace are not covered.

If, from April 2027, you replace a covered device with a device that has IP communication, the replaced device is required to be a JC-STAR ★1 certified product.ANRE, "Frequently asked questions", A11 (our translation)

Even a replacement with the same type requires a connection study application under Article 79, paragraph 1, item 2 of the Transmission and Distribution Business Guidelines. It does not count as a "minor change".

The only exception is "excessive burden". ANRE gives three examples.

In such a case, you consult the local grid operator and submit a plan with three points. If it is accepted, you may for now replace the device with a product of the same type without ★1.

  1. Why you cannot replace it with a ★1 product (with supporting documents)
  2. When all covered devices will be ★1 (for example, the planned year of replacement)
  3. The cybersecurity measures until then

At a seminar in April 2026, it was explained that replacing even one device might require all the devices at the plant to be ★1 (as reported by Orrick). The FAQ of July narrowed this to the "replaced device". If you replace 1 of 30 units, only that 1 is covered.

Low voltage is October because of stock in distribution

Only low voltage is six months later, because old products remain in stock in distribution.

Even after makers introduce products with JC-STAR ★1, a certain amount of stock of old products is expected to remain in the distribution network for some time. We therefore set October 2027 as the start date.OCCTO, 21st Grid Code Review Committee, Material 4 (31 March 2026), p. 3 (our translation)

The Japan Photovoltaic Energy Association (JPEA) asked for a grace period until October also for high voltage and other systems that use the same PCS as low voltage. Material for the 22nd Committee (21 August 2026) says that after discussion it was decided "to proceed as proposed". The grace period was not widened.

Schemes that already require ★1

The grid connection requirement starts in April 2027. The auction and the national subsidy already require ★1. Table 2 shows these two schemes and what each asks for.

Table 2 | Schemes that already require ★1
SchemeFrom whenWhat it asks for
Long-Term Decarbonisation Power Source Auction (FY2025 round)At the bidding procedureState the model number and JC-STAR registration number for the battery's EMS, PCS and so on (bidding guidelines, 3 September 2025)
National subsidy (Grid-Scale Storage System Deployment Support Programme, FY2025 supplementary budget)At application (call open 4 September to 4 November 2026)★1 for BMS, PCS, EMS and so on. A device not covered by ★1 must obtain ★2 before supply starts, if a ★2 standard is later set and covers it

What to check before you buy

How to read this series

COLUMN 52
Overview
All 395 products are ★1. China's 16 largest makers: zero. Start with the numbers
COLUMN 52-2
The list
Grid-scale, residential and other, in one list. Ten labels expire in May 2027
COLUMN 52-3
Existing plants
What happens to existing solar plants
You are reading this one
COLUMN 52-4
Nationality
Countries that screen by nationality and countries that use a label. Mutual recognition is no back door

Frequently asked questions

If I add a battery to an existing solar plant, does the solar PCS also need JC-STAR ★1?

No. ANRE's FAQ asks for ★1 in the devices used for an added battery. It does not ask for existing equipment to be replaced with ★1 devices if it is used as it is. ★1 is needed for the PCS, BMS, EMS, remote monitoring and gateway of the added battery side.

If I apply for the connection study by March 2027, do I avoid ★1?

No. The starting point is the day the grid operator accepted the "contract application". That means the point when the documents are complete and the deposit has been paid. Applying for or receiving the reply to a connection study does not secure the old treatment. ★1 is needed for acceptances on or after 1 April 2027 for extra-high and high voltage, and on or after 1 October 2027 for low voltage (under 50 kW).

When I replace a failed PCS, must it be a JC-STAR ★1 product?

In principle, yes. If, from April 2027, you replace a device with one that has IP communication, the new device is required to have ★1. Only where this would be an "excessive burden", for example because other devices would have to be replaced too, you may consult the local grid operator. If you submit a plan stating (1) why you cannot replace it and the evidence, (2) when everything will be ★1, and (3) the measures until then, you may for now replace it with a product of the same type without ★1.

Is JC-STAR ★1 needed for switching from FIT to FIP or at the end of the FIT period?

Not if you do not add or change equipment. If you add a battery at the same time as the switch to FIP or the end of the FIT period, the added battery needs ★1, but the unchanged existing devices do not.

Primary sources and related articles

Requirement text and FAQ

Schemes that already require ★1

Law firm commentary

Related articles

Supervised by
Shinya Nakashima, Ph.D. (Eng.) — Representative Director, Science X Inc.

Written and supervised on the basis of our work buying grid-scale battery storage projects and selling them on. The JC-STAR counts are our own count of IPA's published list (Excel edition). The reading of the rules rests on published material from ANRE, OCCTO and IPA; where we rely on press reports, the text or table says so. This English edition is a translation of the Japanese original; for legal and regulatory matters, the Japanese primary sources govern. To point out an error, write to s@scix.co.jp.