Battery Storage Market Notes, November 2026 issue

"Grid-scale batteries" are large batteries connected to the power grid that store electricity and release it. They earn money by selling the "capability" to fix surpluses and shortages of electricity. They also use the difference in electricity prices across the day. These notes use published figures and our records to show, in figures and tables, how the market moved in October 2026. From this issue, each issue is named after the month it is published. This issue covers market figures for October 2026 (together with the previous issue, the October 2026 issue, it covers the October market; in the previous issue, only the balancing market used September figures). This issue is built from the latest data published on the day we prepared it. Section 3 shows November 2026 so far, and section 4 shows which source each figure comes from and up to which day.

Science X Inc. · Published November 23, 2026 · A4, 18 pages

Three income sources for a battery storage site (how to read these notes)

A battery storage site (grid-scale battery) earns income from three markets. ① The balancing market (EPRX) is where the "capability" to fix surpluses and shortages of electricity is sold to grid operators. ② Wholesale electricity (JEPX) is the market where electricity is bought and stored when it is cheap and sold when it is expensive. ③ The capacity market (OCCTO) is where the country buys future electricity supply capacity in advance. These notes present the figures in the order of these three markets. The ①②③ at the start of each section title shows which market it covers.

Figure 1  Three income sources for a battery storage site
Figure 1 Three income sources for a battery storage site

Source: Rules of the Japan Electric Power Exchange (JEPX), the Electric Power Reserve Exchange (EPRX) and the Organization for Cross-regional Coordination of Transmission Operators (OCCTO).

Three trends this month

We picked three trends for October 2026 from the figures of the three markets.

The October 2026 figures for wholesale electricity (JEPX) and for our records (new listings on Chikudensho Market and grid connection studies) are the same as in the previous issue (the October 2026 issue). For the capacity market, this issue adds the results of the additional auction (they were not in the previous issue). Figures for part of November 2026 have moved to the Daily Flash. The bid ratio is the volume bid ÷ the volume grid operators asked for. Above 100% means more bids came in than were requested.

November 2026 so far: moved to the Daily Flash

Figures for November 2026 so far (this month to date, the latest day, comparison with last month and by week) are on the Daily Flash, re-fetched from the latest published data every morning. This issue covers the whole previous month.

Data dates in this issue

This table lists the source of each figure in this issue and the last day each data set covers. Figures for the balancing market (EPRX), wholesale electricity (JEPX) and the capacity market (OCCTO) were taken again from the latest data published on the day we prepared the issue. Our records are tallies as of the dates shown in the table.

SourcePeriod coveredTypeDate taken or checked
Balancing market (EPRX), October 2026 figuresOctober 1–31, 2026 (31 days)Preliminary figures (final figures not yet published)November 23, 2026
Balancing market (EPRX), monthly trends (Figure 4, Figure 5 and others)Final figures for April 2024 to September 2026, preliminary figures for October 2026Final figures only for months where they are publishedNovember 23, 2026
Wholesale electricity (JEPX), October 2026 figuresOctober 1–31, 2026 (31 days)Trading results (confirmed cleared values)November 23, 2026
Capacity market (OCCTO)Main auction: delivery FY2024 to FY2029 (latest is FY2029) / additional auction: delivery FY2025 to FY2027 (latest is FY2027). Results for delivery FY2030 had not been published on the date we checkedPublished resultsNovember 23, 2026
Our records, new listings on Chikudensho Market (October 2026)October 1–31, 2026Our records (same figures as the previous issue)As tallied for the previous issue
Our records, tally of grid connection study responsesResponse documents we had received as of October 19, 2026Our tallyOctober 19, 2026

"Final figures" are the values EPRX publishes after the month ends (totals that reflect additional procurement and corrections made after clearing; the "Total (final figures)" row in the published file). "Preliminary figures" are the values published right after clearing. When the final figures come out, that month's figures may change slightly.

① Balancing market (EPRX) | Seven products and prices by area

The balancing market is where grid operators buy, every 30 minutes, the "capability" to fix surpluses and shortages of electricity. Products are divided by how fast output can be changed (Primary reserve acts on frequency changes; Secondary and Tertiary reserves act on instructions from the grid operator). Primary reserve is the fastest, and Tertiary reserve 2 is the slowest. Primary reserve is a product that senses frequency changes by itself and acts. It has two categories, "online" and "offline." In online, the grid operator watches the response over a dedicated line. In offline, no dedicated line is laid, and a record of the response is submitted afterwards. The two are recruited and traded separately, so we show them separately. A Composite product is a bid that offers several products together. Prices are set in yen per 1 kW of capability per 30 min. kW is a unit for how much power can be delivered; it is different from kWh, which measures an amount of electricity. One round of the 30-minute trading is called a "30-minute slot." The figure shows the range of winning prices by area (by the area where the power source is). The thin line runs from the cheapest bid to the most expensive bid in the month. The thick band is the price range that holds 8 out of 10 slots with winning bids. The dot is the average winning price. Nationwide figures are in the table in the "Market figures" section.

Across all products and all areas, the highest average winning price by area in the balancing market (yen/kW per 30 min) was 13.64 yen for Tertiary reserve 2 in Tohoku, and the lowest was 0.38 yen for Tertiary reserve 2 in Shikoku.

Figure 2  Range and average of winning prices by area in the balancing market (October 2026 (1–31), by area where the power source is)
Figure 2 Range and average of winning prices by area in the balancing market (October 2026 (1–31), by area where the power source is)

Source: Trading results (preliminary figures) published by the Electric Power Reserve Exchange (EPRX). Compiled by us.

ProductResponse timeDuration
Primary reserve (online)Within 10 seconds5 minutes or more
Primary reserve (offline)Within 30 secondsNo set duration
Secondary reserve 1Within 5 minutes30 minutes
Secondary reserve 2Within 5 minutes30 minutes
Tertiary reserve 1Within 15 minutes30 minutes
Tertiary reserve 2Within 60 minutes30 minutes
Composite productRequirements of the combined productsRequirements of the combined products

① Balancing market (EPRX) | Grid areas and times where bids win more easily

The clearing rate is the share of the bid volume that won. The higher it is, the more easily bids win. The figure plots the clearing rate of each product by time of day (every 30 minutes) for each grid area (the area where the power source is). Where a line breaks, there were no bids at that time.

Figure 3  Clearing rate in the balancing market (grid area (area where the power source is) × time of day, October 2026 (1–31))
Figure 3 Clearing rate in the balancing market (grid area (area where the power source is) × time of day, October 2026 (1–31))

Source: Trading results (preliminary figures) published by the Electric Power Reserve Exchange (EPRX). Compiled by us.

① Balancing market (EPRX) | Primary reserve (online) became a contest for places

Primary reserve is the fastest product. It acts on frequency changes and changes output within 10 seconds (online) or within 30 seconds (offline). Batteries are often used for it. The left side shows the online category and the right side shows the offline category. The bars are the bid ratio (volume bid ÷ volume grid operators asked for). Above 100% means more bids came in than were requested. Even below 100%, some bids do not win (see the clearing rate in the "Market figures" table). The bars rise when bids increase and also when the requested volume falls. The line is the average winning price. These are monthly figures from April 2024. The source figures are final figures for April 2024 to September 2026 and preliminary figures for October 2026. Final figures are published after the month ends and differ slightly from preliminary figures.

In June 2026, the bid ratio for Primary reserve (online) in the balancing market went over 100% for the first time since April 2024, at 108.6%. In October 2026 it was 145.9%, with an average winning price of 3.22 yen/kW per 30 min. The requested volume went from 3,354.0 MW in April 2024 to 1,095.5 MW in October 2026. Primary reserve (offline) in the balancing market had a bid ratio of 92.4% and an average winning price of 2.69 yen/kW per 30 min in October 2026. Its requested volume went from 943.0 MW in April 2024 to 501.5 MW in October 2026.

Figure 4  Bid ratio (bars) and average winning price (line) for Primary reserve (monthly; online on the left, offline on the right; gold bars are months when bids exceeded the requested volume)
Figure 4 Bid ratio (bars) and average winning price (line) for Primary reserve (monthly; online on the left, offline on the right; gold bars are months when bids exceeded the requested volume)

Source: Trading results published by the Electric Power Reserve Exchange (EPRX) (final figures for months where they have been published, preliminary figures for later months). Compiled by us.

① Balancing market (EPRX) | How prices have moved by product

This shows the average winning price by product since April 2024 (monthly average weighted by winning volume). Trading changed from every 3 hours to every 30 minutes on March 14, 2025 for Tertiary reserve 2, and on March 14, 2026 for Primary reserve to Tertiary reserve 1 and the Composite product. The source figures are final figures for April 2024 to September 2026 and preliminary figures for October 2026. Final figures are published after the month ends and differ slightly from preliminary figures.

The average winning price for Primary reserve (online) in the balancing market went from 2.19 yen in April 2024 to 3.22 yen in October 2026. The highest month was May 2026, at 4.83 yen (yen/kW per 30 min). The average winning price for Tertiary reserve 2 in the balancing market went from 4.70 yen in April 2024 to 2.22 yen in October 2026. The highest month was May 2024, at 6.03 yen (yen/kW per 30 min).

Figure 5  Average winning price by product in the balancing market (yen/kW per 30 min, monthly)
Figure 5 Average winning price by product in the balancing market (yen/kW per 30 min, monthly)

Source: Trading results published by the Electric Power Reserve Exchange (EPRX) (final figures for months where they have been published, preliminary figures for later months). Compiled by us.

① Balancing market (EPRX) | Which hours of the day are expensive

This shows the average winning price by hour for each product in October 2026 (1–31).

For Primary reserve (online) in the balancing market, the October 2026 average winning price was highest in the 17:00 hour at 4.01 yen and lowest in the 8:00 hour at 2.78 yen (yen/kW per 30 min). For Tertiary reserve 2 in the balancing market, it was highest in the 19:00 hour at 9.03 yen and lowest in the 17:00 hour at 0.38 yen (yen/kW per 30 min).

Figure 6  Average winning price by time of day in the balancing market (October 2026 (1–31), yen/kW per 30 min)
Figure 6 Average winning price by time of day in the balancing market (October 2026 (1–31), yen/kW per 30 min)

Source: Trading results (preliminary figures) published by the Electric Power Reserve Exchange (EPRX). Compiled by us.

① Balancing market (EPRX) | Which products batteries are used for

The figure shows the share of the winning volume taken by batteries. The table compares the average winning price of the volume batteries won with the average winning price of the whole product.

For Primary reserve (online) in the balancing market, the battery share in October 2026 was 35.3%, and the average winning price of the volume batteries won was 2.93 yen (3.22 yen overall, yen/kW per 30 min).

Figure 7  Share of batteries in the balancing market (%)
Figure 7 Share of batteries in the balancing market (%)

Source: Trading results (preliminary figures) by power source type published by the Electric Power Reserve Exchange (EPRX). Compiled by us.

ProductVolume won by batteries (yen/kW per 30 min)Whole product (yen/kW per 30 min)
Primary reserve (online)2.933.22
Primary reserve (offline)2.692.69
Secondary reserve 16.083.29
Secondary reserve 25.102.86
Tertiary reserve 15.082.60
Tertiary reserve 264.712.22
Composite product2.962.65

Both are averages weighted by winning volume (October 2026, preliminary figures, nationwide). Batteries account for only 0.8% of the winning volume in Tertiary reserve 2. The nationwide average winning price of the slots where batteries won, weighted by the batteries' winning volume, is 9.35 yen/kW per 30 min. The high average for batteries cannot be explained only by their concentration in high-priced slots. It is because the battery bids themselves are priced high (each winning bid is settled at its own bid price).

① Balancing market (EPRX) | Revenue gathers in a small number of slots

We ranked the month's 30-minute slots with winning bids by revenue (average winning price × winning volume, nationwide), from highest to lowest. For each product, we plotted what share of the month's revenue the top slots hold. The more the curve bulges above the dotted line, the more the revenue gathers in a small number of slots. Tertiary reserve 2 is a product that covers errors in forecasting weather-dependent renewable output. Its price is low in most slots and high in a small number of slots.

In the balancing market in October 2026, the top 10% of slots held 59.8% of the month's revenue for Tertiary reserve 2 and 14.8% for Primary reserve (online).

Figure 8  Share of balancing market revenue that gathers in the top slots (October 2026 (1–31), nationwide)
Figure 8 Share of balancing market revenue that gathers in the top slots (October 2026 (1–31), nationwide)

Source: Trading results (preliminary figures) published by the Electric Power Reserve Exchange (EPRX). Compiled by us.

In October 2026, out of 1,207 slots with winning bids, the top 1% of slots by revenue (average winning price × winning volume) held 10.7% of the month's revenue. There were 92 slots with a nationwide average winning price of 10 yen/kW per 30 min or more, and 281 slots with no winning bids.

Slots with the highest top winning price (by area where the power source is). The top winning price is the price of the single highest winning bid. The average winning price for the same slot and area is shown on the right:

DayTimeAreaTop winning price (yen/kW per 30 min)Average winning price for the same slot and area (yen/kW per 30 min)
October 812:30Kansai87.3715.17
October 813:30Kansai82.3312.25
October 1313:30Kansai82.3322.17
October 1314:00Kansai82.3322.69
October 114:00Chubu80.0034.10

② Wholesale electricity (JEPX) | Average price

Wholesale electricity is the electricity that power companies and retail electricity companies buy and sell. Its price is set on the "spot market" of the Japan Electric Power Exchange (JEPX), where electricity for the next day is traded the day before. "System (nationwide)" is the price when all of Japan is treated as one market (the system price). When transmission lines between regions are congested, prices split by area, from Hokkaido to Kyushu (area prices).

The monthly average wholesale electricity (JEPX) price for System (nationwide) was 22.51 yen/kWh in October 2026, against 11.67 yen/kWh in the same month last year.

Figure 9  Average wholesale electricity price (yen/kWh). Navy is October 2026, grey is the same month last year
Figure 9 Average wholesale electricity price (yen/kWh). Navy is October 2026, grey is the same month last year

Source: Spot market trading results published by the Japan Electric Power Exchange (JEPX). Simple average of 30-minute prices. Compiled by us.

② Wholesale electricity (JEPX) | How the price moves through the day

The wholesale electricity price changes every 30 minutes. The figure shows the shape of one day, made by averaging the prices at the same time across the month. If a battery stores electricity when it is cheap and releases it when it is expensive, the difference becomes the battery's income.

Through the day, the average wholesale electricity price ranged from 19.03 yen around 12:00 to 37.11 yen around 16:30 in Tokyo, and from 4.94 yen around 12:00 to 24.74 yen around 17:30 in Kyushu (yen/kWh).

Figure 10  Peaks and troughs of the wholesale electricity price through the day (October 2026 average, yen/kWh)
Figure 10 Peaks and troughs of the wholesale electricity price through the day (October 2026 average, yen/kWh)

Source: JEPX spot market. Compiled by us.

② Wholesale electricity (JEPX) | How large the price gap is per kWh

For each area, we took the average price of the day's most expensive 4 hours minus the average price of its cheapest 4 hours, and show the monthly average. This equals the difference per kWh when 1 kWh is bought in the cheapest 4 hours and sold in the most expensive 4 hours. It is a simple gap. Electricity lost in charging and discharging and fees are not subtracted, and the order of the cheap and expensive hours is not considered.

The gap between the average of the most expensive 4 hours and the average of the cheapest 4 hours in wholesale electricity (monthly average) was largest in Hokkaido at 29.02 yen/kWh and smallest in Tokyo at 17.14 yen/kWh.

Figure 11  Wholesale electricity price gap: average of the most expensive 4 hours − average of the cheapest 4 hours (October 2026, yen/kWh, monthly average)
Figure 11 Wholesale electricity price gap: average of the most expensive 4 hours − average of the cheapest 4 hours (October 2026, yen/kWh, monthly average)

Source: JEPX spot market. Compiled by us.

Area2-hour price gap (yen/kWh)4-hour price gap (yen/kWh)Days with a 4-hour price gap of 10 yen or more
System (nationwide)22.9520.4229
Hokkaido32.5629.0231
Tohoku27.0924.7430
Tokyo19.6217.1429
Chubu22.3719.9129
Hokuriku21.7119.1831
Kansai21.2218.7131
Chugoku20.9018.9331
Shikoku19.4017.2728
Kyushu21.1919.3031

The price gap is the monthly average of the daily gaps. October 2026 has 31 days of data.

② Wholesale electricity (JEPX) | There is a price gap every day

We show the same 4-hour price gap day by day. The bigger the gap on a day, the more room a battery has to earn from the price gap.

Out of 31 days, the 4-hour wholesale electricity price gap was 10 yen or more on 31 days in Hokkaido, Hokuriku, Kansai, Chugoku and Kyushu, 30 days in Tohoku, 29 days in System (nationwide), Tokyo and Chubu, and 28 days in Shikoku.

Figure 12  Daily wholesale electricity price gap (average of the day's most expensive 4 hours − average of its cheapest 4 hours, yen/kWh)
Figure 12 Daily wholesale electricity price gap (average of the day's most expensive 4 hours − average of its cheapest 4 hours, yen/kWh)

Source: JEPX spot market. Compiled by us.

③ Capacity market (OCCTO) | A market that buys future supply capacity

The capacity market buys electricity supply capacity 4 years ahead through an auction held once a year. The price is set in yen per kW per year. The left figure shows the clearing prices of past main auctions. The right figure shows the battery and pumped hydro capacity cleared in the Long-Term Decarbonization Power Source Auction (a separate auction that promises capacity income, in principle for 20 years, for things such as new decarbonized power sources). These are published once a year, so they do not change every month. The latest main auction is for delivery FY2029 (published January 2026), and the latest additional auction is for delivery FY2027 (published August 2026). The clearing prices of the additional auction (an auction that buys, in the year before delivery, the supply capacity the main auction did not secure) are in the "Market figures" table.

The capacity market main auction clearing price for Tokyo from delivery FY2024 to FY2029 was 14,137 yen → 3,495 yen → 5,834 yen → 9,555 yen → 14,812 yen → 15,111 yen (yen/kW). In the capacity market's Long-Term Decarbonization Power Source Auction, the battery and pumped hydro capacity cleared in the FY2025 round was 819 MW for lithium-ion batteries and pumped hydro (excluding new builds), and 886 MW for non-lithium-ion batteries, pumped hydro (new builds) and LDES. Both are once-a-year values, so they are the latest published figures and do not change every month.

Figure 13  Capacity market clearing prices (left, yen/kW) and battery and pumped hydro capacity cleared in the Long-Term Decarbonization Power Source Auction (right, in units of 10,000 kW)
Figure 13 Capacity market clearing prices (left, yen/kW) and battery and pumped hydro capacity cleared in the Long-Term Decarbonization Power Source Auction (right, in units of 10,000 kW)

Source: Results and capacity securing contract materials published by the Organization for Cross-regional Coordination of Transmission Operators (OCCTO) (sources are listed in the "Assumptions and terms" section). As published.

Our records | Where battery storage projects are increasing

We counted the projects newly listed in October 2026 on our Chikudensho Market (our marketplace for grid-scale battery sites), by grid operator area. These are figures for projects we handled, not the number for the whole market. Transfer of rights hands over the rights to the land and power. Completed-build handover hands over the facility once it is built.

New listings on our Chikudensho Market in October 2026 were 77 projects, 309.1 MW. By grid area, Tokyo had 33 projects, 99.8 MW; Tohoku had 8 projects, 73.4 MW; and Chubu had 11 projects, 69.9 MW.

Figure 14  Output (MW) of projects newly listed on Chikudensho Market in October 2026
Figure 14 Output (MW) of projects newly listed on Chikudensho Market in October 2026

Source: Our Chikudensho Market records (project locations are given only down to the grid area; prices and parties are not shown).

Our records | How many months and how much it takes to connect to the grid

A grid connection study is a procedure where the grid operator checks "whether you can connect at this location, and how much the work will cost." The grid connection cost contribution is the part of the connection work cost that the applicant pays. Of the response documents we received, we tallied only high-voltage cases (connecting to 6,600 V distribution lines), by grid area. Extra-high voltage is not included. Grid areas with fewer than 5 cases are not shown.

For grid connection study responses (high voltage only, as of October 19, 2026), the median construction period was 8.0 months in Tokyo, 12.0 months in Chubu, 12.0 months in Kansai, 12.5 months in Kyushu and 17.0 months in Tohoku (5 cases). The median grid connection cost contribution was ¥3.02 million in Tokyo, ¥3.70 million in Chubu, ¥12.34 million in Kansai, ¥12.50 million in Kyushu and ¥32.35 million in Tohoku (8 cases).

Figure 15  Medians of grid connection study responses (high voltage) by grid area (left: months of construction work, right: grid connection cost contribution, excluding tax)
Figure 15 Medians of grid connection study responses (high voltage) by grid area (left: months of construction work, right: grid connection cost contribution, excluding tax)

Source: Tally of the high-voltage cases among the grid connection study responses we received from general transmission and distribution operators (as of October 19, 2026).

Market figures (tables you can use as they are)

We put the figures behind the charts into tables so you can use them in your materials: ① nationwide figures by product for the balancing market (bid ratio, clearing rate, price, battery share), ② figures by area and trading volume for wholesale electricity (JEPX), and ③ capacity market clearing prices.

Balancing market (October 2026, preliminary figures, nationwide)

ProductRequested volume (MW)Bid volume (MW)Winning volume (MW)Bid ratio (bids ÷ requested)Clearing rate (won ÷ bids)Average winning price (yen/kW per 30 min)Battery share
Primary reserve (online)1,095.51,598.11,160.7145.9%72.6%3.2235.3%
Primary reserve (offline)501.5463.5299.892.4%64.7%2.69100.0%
Secondary reserve 1928.91,673.0953.3180.1%57.0%3.292.9%
Secondary reserve 2943.23,103.11,867.7329.0%60.2%2.861.2%
Tertiary reserve 12,563.94,829.12,700.3188.4%55.9%2.600.9%
Tertiary reserve 2387.21,617.0369.1417.6%22.8%2.220.8%
Composite product3,377.55,575.53,271.5165.1%58.7%2.6512.7%

Volumes are averages per 30-minute slot. Products with a bid ratio below 100% did not get enough bids for the requested volume. The clearing rate is the share of the bid volume that won.

Wholesale electricity, JEPX spot market (October 2026, by area, yen/kWh)

AreaMonthly averageSame month last yearDaytime (8:00–16:00)Evening (16:00–20:00)4-hour price gapHighestSlots at 30 yen or moreSlots at 0.01 yen
System (nationwide)22.5111.6716.0231.0620.4247.8822039
Hokkaido20.4912.8911.3132.2529.02105.0030367
Tohoku23.9912.0815.7834.1924.7450.0143795
Tokyo27.0213.0623.1234.6917.1450.0146616
Chubu25.4611.6820.3833.5519.9146.4538724
Hokuriku19.7011.2718.2926.9219.1846.4521824
Kansai19.5011.2718.2226.7618.7146.4521529
Chugoku15.6311.129.8623.1018.9344.796379
Shikoku11.449.287.5016.6117.2737.5123146
Kyushu15.0710.748.3123.1019.3044.795391

Trading volume (October 2026, total for 31 days): total cleared volume 30,319 million kWh (same month last year 22,279 million kWh), sell bid volume 45,218 million kWh, buy bid volume 38,191 million kWh.

Capacity market main auction area prices (yen/kW per year)

Delivery fiscal yearHokkaidoTohokuTokyoChubuHokurikuKansaiChugokuShikokuKyushu
FY202414,13714,13714,13714,13714,13714,13714,13714,13714,137
FY20255,2423,4953,4953,4953,4953,4953,4953,4955,242
FY20268,7495,8335,8345,8325,8325,8325,8325,8328,748
FY202713,2879,0449,5557,8237,6387,6387,6387,63811,457
FY202814,81214,81214,81210,2808,7858,7858,7858,78513,177
FY202914,97215,11115,11112,38812,38812,38812,38812,38815,112

Capacity market additional auction area prices (yen/kW per year; only areas where it was held)

Delivery fiscal year of the additional auctionHokkaidoTohokuTokyoChubuHokurikuKansaiChugokuShikokuKyushu
FY202513,761—3,495—————5,029
FY20268,7498,7498,7498,7498,2138,2138,2138,2138,591
FY202710,36110,36110,36110,36110,36110,36110,36110,36110,361

The additional auction buys, in the year before delivery, the supply capacity the main auction did not secure. "—" means it was not held in that area (for delivery FY2025, it was held only in Hokkaido, Tokyo and Kyushu).

Battery and pumped hydro capacity cleared in the Long-Term Decarbonization Power Source Auction (10,000 kW)

Bidding yearCategoryCleared capacity (10,000 kW)
FY2023 roundBatteries and pumped hydro166.9
FY2024 roundOperating duration of 3 hours or more and less than 6 hours96.1
FY2024 roundOperating duration of 6 hours or more76.9
FY2025 roundLithium-ion batteries and pumped hydro (excluding new builds)81.9
FY2025 roundNon-lithium-ion batteries, pumped hydro (new builds) and LDES88.6

Upcoming dates

From this month to three months ahead (November 2026 to February 2027), we list only the events that battery operators, developers and investors act on and whose dates we checked on the source page. Items dated "around," "planned" or "targeted," and items we have not checked, are not listed. Items given only by month are listed only with a note on what needs checking. "Registration of expected capacity" in the Long-Term Decarbonization Power Source Auction is a registration step to complete before bidding (applying). "Basis data for calculating bid capacity" are the figures used to calculate the capacity to bid (both terms follow the wording of the auction guidelines).

DateEventDetailsWho actsSource
December 9–15, 2026Long-Term Decarbonization Power Source Auction (bidding year 2026): registration of expected capacityRegistration of expected capacity is accepted December 9–15, and review runs December 16–25. Bidding is in January 2027.Battery developers and owners (businesses considering bidding)[1]
January 19–26, 2027Long-Term Decarbonization Power Source Auction (bidding year 2026): bids acceptedBids are accepted January 19–26. Requested capacity: 400 MW of batteries (lithium-ion) and 400 MW of non-lithium batteries. Registration of the basis data for calculating bid capacity runs January 27 to February 3.Battery developers and owners[1]
February 18, 2027Completion deadline for SII (the organization that handles national subsidy administration) subsidy projects under the Reiwa 7 fiscal year supplementary budget (single-year)The project period runs from the grant decision date to February 18, 2027. Multi-year projects run from the grant decision date up to January 19, 2029. Contracts and orders made before the grant decision are not eligible for the subsidy.Businesses selected for the subsidy[2]

Number of projects on Chikudensho Market

This is the number of projects visible to buyers on Chikudensho Market (https://dealroom.scix.co.jp). It comes from the same source as our public market data (https://www.scix.co.jp/market-data), and uses the count at the end of each week. This section uses the count for the last week of October 2026. The current count is on the market data page.

Assumptions and terms

How to read the numbers in this issue

Figures across issues

How to cite

You are welcome to quote the figures and charts on this page. Please give the source as follows.

Source: Science X Inc., “Battery Storage Market Notes, November 2026 issue” (updated 2026-11-23), https://www.scix.co.jp/en/report/2026-11

Page: https://www.scix.co.jp/en/report/2026-11 · Updated:

The figures are tallies of published data and our own records. The price spread is a difference in price per kWh and does not show actual revenue. How we compiled them is in the last section, “Assumptions and terms”. Figures across issues are on market data (CSV), and the reuse terms are in the citation guide.

Each month's update also arrives in our LinkedIn newsletter, “Japan grid-scale BESS: primary data”. Subscribe to the newsletter →

Want to see the projects behind these numbers? Visit Chikudensho Market

On Chikudensho Market, our marketplace for battery storage sites, you can browse current listings without registering. Prices and documents are available after free registration, where you agree to a confidentiality undertaking on the registration screen (no signed paper is needed).

Register free to see prices and documents → Browse projects on Chikudensho Market